Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
712251
Final Estimate Of Actual Costs Through End Of Phase Amount
217664
Total Phase Actual Spending Amount
214687
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
11424375
Final Estimate Of Actual Costs Through End Of Phase Amount
10580041
Total Phase Actual Spending Amount
1613517
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/28/2022
Project Phase Planned End Date
6/15/2023
Project Phase Actual End Date
6/15/2023
Project Budget Amount
507749
Final Estimate Of Actual Costs Through End Of Phase Amount
692974
Total Phase Actual Spending Amount
603308
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/16/2022
Project Phase Planned End Date
11/16/2022
Project Phase Actual End Date
12/28/2022
Project Budget Amount
101549
Final Estimate Of Actual Costs Through End Of Phase Amount
167392
Total Phase Actual Spending Amount
160128
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-REMOVE SINK ALONG WITH THE CABINETS. 2' X 3'. 2' HIGH ABATE AND REPLACE FLOORS 20 SQFT. ADDRESS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
4/27/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/16/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
21333
Total Phase Actual Spending Amount
21333
Dsf Number S
SCA0000075864
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-RESPONSE ACTION NEEDED DUE TO OBSERVED DAMAGE FROM PS 3235 - ROOM 235 - 9X9 FT 1007A - TOILET C
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
9/15/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
7/10/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
95938
Total Phase Actual Spending Amount
3343
Dsf Number S
SCA0000074918
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE FLOOR TILES IN ROOMS: 337, 204 AND 335
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/19/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/20/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
87076
Total Phase Actual Spending Amount
3377
Dsf Number S
SCA0000075628
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163523
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: I.S. 2 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
I.S. 2 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY24 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/14/2025
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
352799
Total Phase Actual Spending Amount
342085
Dsf Number S
DSF0001085933
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY24 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
125000
Final Estimate Of Actual Costs Through End Of Phase Amount
125000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001085934
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY24 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
125000
Final Estimate Of Actual Costs Through End Of Phase Amount
125000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001085935
13
Project Geographic District : 13 • Project Building Identifier: K003 • Project School Name: P.S. 3 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K003
Project School Name
P.S. 3 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-REMOVE PIPE INSULATION FROM STEAM RETURN LINE LOCATED IN THE FAN RM. #18 SPACE ID# 1018 AREA
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/18/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/7/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
984
Total Phase Actual Spending Amount
234
Dsf Number S
SCA0000075615
13
Project Geographic District : 13 • Project Building Identifier: K003 • Project School Name: P.S. 3 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K003
Project School Name
P.S. 3 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPAIR SOFFIT PLASTER IN ROOM 109 AND CEILING PLA
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
6/1/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
7/28/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000076070
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
CM,Art,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/3/2026
Project Budget Amount
10668320
Final Estimate Of Actual Costs Through End Of Phase Amount
9264256
Total Phase Actual Spending Amount
6828305
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/3/2026
Project Budget Amount
75678395
Final Estimate Of Actual Costs Through End Of Phase Amount
69904366
Total Phase Actual Spending Amount
64771110
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/16/2022
Project Phase Planned End Date
4/5/2023
Project Phase Actual End Date
4/28/2023
Project Budget Amount
6000930
Final Estimate Of Actual Costs Through End Of Phase Amount
3159242
Total Phase Actual Spending Amount
2785545
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/3/2022
Project Phase Planned End Date
9/15/2022
Project Phase Actual End Date
9/15/2022
Project Budget Amount
1333540
Final Estimate Of Actual Costs Through End Of Phase Amount
918515
Total Phase Actual Spending Amount
918515
Dsf Number S
DSF0000890667
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
500000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163524
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY23 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/2/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
279578
Total Phase Actual Spending Amount
4753
Dsf Number S
DSF0001035360
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/19/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
220310
Total Phase Actual Spending Amount
46982
Dsf Number S
DSF0001034976
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
DEP GREEN INFRASTRUCTURE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/18/2020
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
751864
Total Phase Actual Spending Amount
461669
Dsf Number S
DSF0000865729
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
Fast Track Projects
Project Description
WINDOWS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/22/2023
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
23961403
Total Phase Actual Spending Amount
22681271
Dsf Number S
DSF0001085193
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: K140 SPED - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
K140 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
9750
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163525
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY27 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
418400
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001164500
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/8/2022
Project Phase Planned End Date
8/6/2024
Project Budget Amount
1175650
Final Estimate Of Actual Costs Through End Of Phase Amount
1594495
Total Phase Actual Spending Amount
1565423
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/8/2022
Project Phase Planned End Date
8/6/2024
Project Budget Amount
18894375
Final Estimate Of Actual Costs Through End Of Phase Amount
17742865
Total Phase Actual Spending Amount
15578747
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/10/2020
Project Phase Planned End Date
8/31/2021
Project Phase Actual End Date
8/9/2021
Project Budget Amount
839750
Final Estimate Of Actual Costs Through End Of Phase Amount
938768
Total Phase Actual Spending Amount
899427
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/17/2020
Project Phase Planned End Date
2/23/2021
Project Phase Actual End Date
12/9/2020
Project Budget Amount
167950
Final Estimate Of Actual Costs Through End Of Phase Amount
229149
Total Phase Actual Spending Amount
215149
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
6000
Final Estimate Of Actual Costs Through End Of Phase Amount
6000
Total Phase Actual Spending Amount
40
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
88000
Final Estimate Of Actual Costs Through End Of Phase Amount
88000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
6000
Final Estimate Of Actual Costs Through End Of Phase Amount
6000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
ADA SHELTER COMPLIANCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/17/2018
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
101671
Total Phase Actual Spending Amount
101671
Dsf Number S
DSF0000865885
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
15163
Total Phase Actual Spending Amount
688
Dsf Number S
DSF0001163526
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
11/12/2025
Project Phase Planned End Date
FTK
Project Phase Actual End Date
5/10/2026
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
189915
Total Phase Actual Spending Amount
149943
Dsf Number S
DSF0001112512
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/15/2026
Project Phase Planned End Date
5/10/2027
Project Budget Amount
67764
Final Estimate Of Actual Costs Through End Of Phase Amount
58189
Total Phase Actual Spending Amount
32400
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/15/2026
Project Phase Planned End Date
5/10/2027
Project Budget Amount
170056
Final Estimate Of Actual Costs Through End Of Phase Amount
163418
Total Phase Actual Spending Amount
4984
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/13/2025
Project Phase Planned End Date
9/8/2025
Project Phase Actual End Date
8/26/2025
Project Budget Amount
11830
Final Estimate Of Actual Costs Through End Of Phase Amount
8366
Total Phase Actual Spending Amount
8366
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/12/2025
Project Phase Planned End Date
7/11/2025
Project Phase Actual End Date
3/13/2025
Project Budget Amount
2958
Final Estimate Of Actual Costs Through End Of Phase Amount
2091
Total Phase Actual Spending Amount
2091
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/10/2022
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
476741
Total Phase Actual Spending Amount
449900
Dsf Number S
SCA0000070859
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: P.S. 7 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
P.S. 7 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY18 RESO A IP SECURITY CAMERAS
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
345611
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0000866412
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: P.S. 7 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
P.S. 7 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY27 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
600000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001164451
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
4/16/2025
Project Phase Planned End Date
3/11/2026
Project Phase Actual End Date
7/8/2026
Project Budget Amount
113101
Final Estimate Of Actual Costs Through End Of Phase Amount
108553
Total Phase Actual Spending Amount
107678
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
4/16/2025
Project Phase Planned End Date
3/11/2026
Project Phase Actual End Date
7/8/2026
Project Budget Amount
161472
Final Estimate Of Actual Costs Through End Of Phase Amount
146045
Total Phase Actual Spending Amount
123531
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/20/2024
Project Phase Planned End Date
9/13/2024
Project Phase Actual End Date
7/16/2024
Project Budget Amount
12528
Final Estimate Of Actual Costs Through End Of Phase Amount
11652
Total Phase Actual Spending Amount
11652
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/11/2024
Project Phase Planned End Date
5/10/2024
Project Phase Actual End Date
1/11/2024
Project Budget Amount
2784
Final Estimate Of Actual Costs Through End Of Phase Amount
2913
Total Phase Actual Spending Amount
2913
Dsf Number S
DSF0001087362
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/17/2026
Project Phase Planned End Date
5/12/2027
Project Budget Amount
130165
Final Estimate Of Actual Costs Through End Of Phase Amount
105723
Total Phase Actual Spending Amount
6584
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/17/2026
Project Phase Planned End Date
5/12/2027
Project Budget Amount
194235
Final Estimate Of Actual Costs Through End Of Phase Amount
189268
Total Phase Actual Spending Amount
5930
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/10/2025
Project Phase Planned End Date
3/11/2026
Project Phase Actual End Date
3/9/2026
Project Budget Amount
13512
Final Estimate Of Actual Costs Through End Of Phase Amount
14680
Total Phase Actual Spending Amount
14680
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/3/2025
Project Phase Planned End Date
1/6/2026
Project Phase Actual End Date
9/10/2025
Project Budget Amount
3378
Final Estimate Of Actual Costs Through End Of Phase Amount
3670
Total Phase Actual Spending Amount
3670
Dsf Number S
DSF0001087363