Project Geographic District
6
Project Building Identifier
M152
Project School Name
P.S. 152 - MANHATTAN
Project Description
ROOFS / PARAPETS / WINDOWS / EXTERIOR MASONRY / EMERGENCY GENERATOR / FLOOD ELIMINATION
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/25/2023
Project Phase Planned End Date
6/10/2024
Project Phase Actual End Date
4/25/2024
Project Budget Amount
1131307
Final Estimate Of Actual Costs Through End Of Phase Amount
569699
Total Phase Actual Spending Amount
561280
Dsf Number S
DSF0001018857, DSF0001018858, DSF0001018859, DSF0001018860, DSF0001087210, DSF0001087209