Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
4
Project Geographic District : 4 • Project Building Identifier: M155 • Project School Name: P.S. 155 - MANHATTAN
Project Geographic District
4
Project Building Identifier
M155
Project School Name
P.S. 155 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-OIL TANK LINE/PIPE INSULATION ABATEMENT FOR ISOLATION VALVE INSTALLS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/6/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000075400
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001163674
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: YORKVILLE EAST MIDDLE SCHOOL
Project Geographic District
2
Project Building Identifier
M158
Project School Name
YORKVILLE EAST MIDDLE SCHOOL
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001163675
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY23 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/16/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
229362
Total Phase Actual Spending Amount
200370
Dsf Number S
DSF0001035695
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
400000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112821
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA ENHANCEMENT EXPERIENCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/31/2025
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
933334
Total Phase Actual Spending Amount
366238
Dsf Number S
DSF0001111656
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
139193
Final Estimate Of Actual Costs Through End Of Phase Amount
139193
Total Phase Actual Spending Amount
2935
Dsf Number S
DSF0001125093
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
542617
Final Estimate Of Actual Costs Through End Of Phase Amount
542617
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001125093
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Design
Project Status Name
In-Progress
Project Phase Actual Start Date
6/24/2026
Project Phase Planned End Date
12/1/2026
Project Budget Amount
37747
Final Estimate Of Actual Costs Through End Of Phase Amount
37747
Total Phase Actual Spending Amount
5602
Dsf Number S
DSF0001125093
2
Project Geographic District : 2 • Project Building Identifier: M158 • Project School Name: P.S. 158 - MANHATTAN
Project Geographic District
2
Project Building Identifier
M158
Project School Name
P.S. 158 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/16/2025
Project Phase Planned End Date
2/19/2026
Project Phase Actual End Date
6/5/2026
Project Budget Amount
9437
Final Estimate Of Actual Costs Through End Of Phase Amount
15997
Total Phase Actual Spending Amount
1400
Dsf Number S
DSF0001125093
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
250000
Dsf Number S
DSF0001163298
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
DOE - RESOA
Project Description
RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/13/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
65741
Dsf Number S
DSF0001085317
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
10/16/2019
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
205755
Total Phase Actual Spending Amount
130840
Dsf Number S
DSF0000889608
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA ENHANCEMENT EXPERIENCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/6/2024
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
313099
Dsf Number S
DSF0001085737
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
FACILITY ENHANCEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/23/2024
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
578188
Total Phase Actual Spending Amount
414296
Dsf Number S
DSF0001112140
5
Project Geographic District : 5 • Project Building Identifier: M161 • Project School Name: P.S. 161 - MANHATTAN
Project Geographic District
5
Project Building Identifier
M161
Project School Name
P.S. 161 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-/ABATE RADIATOR COVERS AND RADIATOR INSULATION WALL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
11/6/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
3/10/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
845
Total Phase Actual Spending Amount
95
Dsf Number S
SCA0000075119
3
Project Geographic District : 3 • Project Building Identifier: M163 • Project School Name: P.S. 163 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M163
Project School Name
P.S. 163 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
VACUUM CONDENSATE PUMPS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
11/15/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
61502
Dsf Number S
DSF0001008558
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 223 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 223 - MANHATTAN
Project Type
DIIT - RESOA
Project Description
FY24 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
Complete
Project Phase Actual Start Date
12/12/2025
Project Phase Planned End Date
DIIR
Project Phase Actual End Date
3/12/2026
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
50000
Total Phase Actual Spending Amount
50000
Dsf Number S
DSF0001086242
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY23 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/22/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
383835
Total Phase Actual Spending Amount
364345
Dsf Number S
DSF0001035696
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA ENHANCEMENT EXPERIENCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/9/2024
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
341409
Total Phase Actual Spending Amount
448
Dsf Number S
DSF0001085738
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 223 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 223 - MANHATTAN
Project Type
Fast Track Projects
Project Description
FY25 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
259080
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112823
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 223 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 223 - MANHATTAN
Project Type
Fast Track Projects
Project Description
FY26 LSP RESO A PLAYGROUND UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
80000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163676
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES / PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
1/12/2027
Project Budget Amount
134418
Final Estimate Of Actual Costs Through End Of Phase Amount
147124
Total Phase Actual Spending Amount
146610
Dsf Number S
DSF0001035195, DSF0001083872
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/15/2024
Project Phase Planned End Date
2/10/2027
Project Budget Amount
541450
Final Estimate Of Actual Costs Through End Of Phase Amount
818272
Total Phase Actual Spending Amount
812599
Dsf Number S
DSF0001018989, DSF0001018990, DSF0001018991
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/15/2024
Project Phase Planned End Date
2/10/2027
Project Budget Amount
8701876
Final Estimate Of Actual Costs Through End Of Phase Amount
7943545
Total Phase Actual Spending Amount
2708317
Dsf Number S
DSF0001018989, DSF0001018990, DSF0001018991
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES / PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/11/2025
Project Phase Planned End Date
1/12/2027
Project Budget Amount
1672457
Final Estimate Of Actual Costs Through End Of Phase Amount
1585401
Total Phase Actual Spending Amount
378270
Dsf Number S
DSF0001035195, DSF0001083872
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
6/14/2023
Project Phase Planned End Date
11/16/2023
Project Phase Actual End Date
10/27/2023
Project Budget Amount
386750
Final Estimate Of Actual Costs Through End Of Phase Amount
465972
Total Phase Actual Spending Amount
432692
Dsf Number S
DSF0001018989, DSF0001018990, DSF0001018991
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES / PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/11/2023
Project Phase Planned End Date
2/15/2024
Project Phase Actual End Date
4/19/2024
Project Budget Amount
82502
Final Estimate Of Actual Costs Through End Of Phase Amount
89473
Total Phase Actual Spending Amount
63517
Dsf Number S
DSF0001035195, DSF0001083872
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
ROOFS / PARAPETS / EXTERIOR MASONRY
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
7/20/2022
Project Phase Planned End Date
12/6/2022
Project Phase Actual End Date
5/4/2023
Project Budget Amount
77350
Final Estimate Of Actual Costs Through End Of Phase Amount
148063
Total Phase Actual Spending Amount
143487
Dsf Number S
DSF0001018989, DSF0001018990, DSF0001018991
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA CIP
Project Description
SCIENCE LAB UPGRADES / PATH OF TRAVEL SCIENCE LAB UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
10/12/2022
Project Phase Planned End Date
7/14/2023
Project Phase Actual End Date
9/28/2023
Project Budget Amount
16926
Final Estimate Of Actual Costs Through End Of Phase Amount
84803
Total Phase Actual Spending Amount
84803
Dsf Number S
DSF0001035195, DSF0001083872
6
Project Geographic District : 6 • Project Building Identifier: M164 • Project School Name: I.S. 328 - MANHATTAN
Project Geographic District
6
Project Building Identifier
M164
Project School Name
I.S. 328 - MANHATTAN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/3/2022
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
1010151
Total Phase Actual Spending Amount
1008819
Dsf Number S
SCA0000071088
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
DOE - Lead Paint
Project Description
LEAD PAINT ABATEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
7/8/2025
Project Phase Planned End Date
DOEL
Project Budget Amount
DOEL
Final Estimate Of Actual Costs Through End Of Phase Amount
51000
Dsf Number S
NULL
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY19 RESO A AUDITORIUM UPGRADE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/9/2026
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
897374
Total Phase Actual Spending Amount
246256
Dsf Number S
DSF0000890822
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: I.S. 862 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
I.S. 862 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
CAFETERIA ENHANCEMENT EXPERIENCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
12/22/2023
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
230678
Total Phase Actual Spending Amount
38528
Dsf Number S
DSF0001085739
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
126602
Final Estimate Of Actual Costs Through End Of Phase Amount
164029
Total Phase Actual Spending Amount
162769
Dsf Number S
DSF0000890587
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
683061
Final Estimate Of Actual Costs Through End Of Phase Amount
683061
Total Phase Actual Spending Amount
9018
Dsf Number S
DSF0000890587
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
10/27/2020
Project Phase Planned End Date
7/28/2021
Project Phase Actual End Date
7/28/2021
Project Budget Amount
52996
Final Estimate Of Actual Costs Through End Of Phase Amount
158351
Total Phase Actual Spending Amount
158351
Dsf Number S
DSF0000890587
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP
Project Description
RPZ BACKFLOW PREVENTION DEVICES
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
5/15/2020
Project Phase Planned End Date
1/29/2021
Project Phase Actual End Date
10/19/2020
Project Budget Amount
11777
Final Estimate Of Actual Costs Through End Of Phase Amount
39586
Total Phase Actual Spending Amount
39586
Dsf Number S
DSF0000890587
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A GYMNASIUM UPGRADE / PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
117483
Final Estimate Of Actual Costs Through End Of Phase Amount
117483
Total Phase Actual Spending Amount
33354
Dsf Number S
DSF0001035699, DSF0001035700
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A GYMNASIUM UPGRADE / PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
1896846
Final Estimate Of Actual Costs Through End Of Phase Amount
1896846
Total Phase Actual Spending Amount
19075
Dsf Number S
DSF0001035699, DSF0001035700
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A GYMNASIUM UPGRADE / PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
11/7/2023
Project Phase Planned End Date
3/14/2024
Project Phase Actual End Date
4/22/2024
Project Budget Amount
119795
Final Estimate Of Actual Costs Through End Of Phase Amount
111483
Total Phase Actual Spending Amount
101929
Dsf Number S
DSF0001035699, DSF0001035700
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A GYMNASIUM UPGRADE / PATH OF TRAVEL RESO A GYMNASIUM UPGRADE
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/13/2023
Project Phase Planned End Date
7/13/2023
Project Phase Actual End Date
11/7/2023
Project Budget Amount
26143
Final Estimate Of Actual Costs Through End Of Phase Amount
26143
Total Phase Actual Spending Amount
26143
Dsf Number S
DSF0001035699, DSF0001035700
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION- SWB @ M165
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/25/2026
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
181000
Total Phase Actual Spending Amount
116810
Dsf Number S
SCA0000075476
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT FLOOR TILES MASTIC LVL 5 9X9 RED - 5400 FLOOR TILE BORDER L
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
5/19/2026
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
750
Total Phase Actual Spending Amount
0
Dsf Number S
SCA0000076000
3
Project Geographic District : 3 • Project Building Identifier: M165 • Project School Name: P.S. 165 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M165
Project School Name
P.S. 165 - MANHATTAN
Project Type
SCA IEH
Project Description
PO18-ROOM 201, 9X9 ACM TILES NEED TO BE REMOVED AND SUB-FLOOR NEEDS TO BE REPLACED AS WELL AS VINYL
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
11/24/2025
Project Phase Planned End Date
IEH
Project Phase Actual End Date
1/20/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
39539
Total Phase Actual Spending Amount
248
Dsf Number S
SCA0000075158
3
Project Geographic District : 3 • Project Building Identifier: M166 • Project School Name: P.S. 166 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M166
Project School Name
P.S. 166 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY23 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/5/2024
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
40790
Total Phase Actual Spending Amount
7991
Dsf Number S
DSF0001035701
3
Project Geographic District : 3 • Project Building Identifier: M166 • Project School Name: P.S. 166 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M166
Project School Name
P.S. 166 - MANHATTAN
Project Type
DOE - RESOA
Project Description
FY24 RESO A SUPPLEMENTAL COOLING
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
361942
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001086243
3
Project Geographic District : 3 • Project Building Identifier: M166 • Project School Name: P.S. 166 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M166
Project School Name
P.S. 166 - MANHATTAN
Project Type
DOE - Skilled Trades
Project Description
BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/16/2021
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
196808
Total Phase Actual Spending Amount
196808
Dsf Number S
DSF0000889609
3
Project Geographic District : 3 • Project Building Identifier: M166 • Project School Name: P.S. 166 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M166
Project School Name
P.S. 166 - MANHATTAN
Project Type
Fast Track Projects
Project Description
FY25 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
3508
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001112824
3
Project Geographic District : 3 • Project Building Identifier: M166 • Project School Name: P.S. 166 - MANHATTAN
Project Geographic District
3
Project Building Identifier
M166
Project School Name
P.S. 166 - MANHATTAN
Project Type
SCA Furniture & Equipment
Project Description
FY20 RESO A MOBILE SCIENCE LAB
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
80000
Final Estimate Of Actual Costs Through End Of Phase Amount
80000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001083870