Project Geographic District
6
Project Building Identifier
M173
Project School Name
P.S./I.S. 173 - MANHATTAN
Project Description
FLOOD ELIMINATION / PARAPETS / EXTERIOR MASONRY / PAVED AREAS- CONCRETE / ROOFS
Project Phase Name
CM,F&E
Project Status Name
Complete
Project Phase Actual Start Date
8/13/2018
Project Phase Planned End Date
8/11/2020
Project Phase Actual End Date
2/22/2026
Project Budget Amount
921201
Final Estimate Of Actual Costs Through End Of Phase Amount
2759788
Total Phase Actual Spending Amount
2735213
Dsf Number S
DSF0000876476, DSF0000876478, DSF0000876479, DSF0000876485, DSF0000889082