Project Geographic District
6
Project Building Identifier
M189
Project School Name
P.S. 189 - MANHATTAN
Project Description
FLOOD ELIMINATION / ROOFS / PARAPETS / EXTERIOR MASONRY / PLAYGROUND
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
2/28/2018
Project Phase Planned End Date
7/30/2018
Project Phase Actual End Date
5/17/2018
Project Budget Amount
735179
Final Estimate Of Actual Costs Through End Of Phase Amount
1312370
Total Phase Actual Spending Amount
1219204
Dsf Number S
DSF0000876592, DSF0000876594, DSF0000876595, DSF0000876596, DSF0000889278