Project Geographic District
15
Project Building Identifier
K032
Project School Name
P.S. 32 - BROOKLYN
Project Description
FLOOD ELIMINATION / PARAPETS / ROOFS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/10/2025
Project Phase Planned End Date
5/13/2026
Project Phase Actual End Date
4/16/2026
Project Budget Amount
374151
Final Estimate Of Actual Costs Through End Of Phase Amount
425176
Total Phase Actual Spending Amount
293302
Dsf Number S
DSF0001088395, DSF0001088397, DSF0001113800