Capital Project Schedules and Budgets

List of capital projects with managing organization, phase status and project costs.

Housing & Development School Construction Authority (SCA) Dataset 2xh6-psuq 14 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
710850
Final Estimate Of Actual Costs Through End Of Phase Amount
174263
Total Phase Actual Spending Amount
167442
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/22/2025
Project Phase Planned End Date
3/9/2028
Project Budget Amount
11424375
Final Estimate Of Actual Costs Through End Of Phase Amount
10633656
Total Phase Actual Spending Amount
704644
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/28/2022
Project Phase Planned End Date
6/15/2023
Project Phase Actual End Date
6/15/2023
Project Budget Amount
507749
Final Estimate Of Actual Costs Through End Of Phase Amount
692974
Total Phase Actual Spending Amount
590616
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA CIP
Project Description
FULL PROGRAM ACCESSIBILITY / ROOFS / FIRE ALARM SYSTEM REPLACEMENT
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/16/2022
Project Phase Planned End Date
11/16/2022
Project Phase Actual End Date
12/28/2022
Project Budget Amount
101549
Final Estimate Of Actual Costs Through End Of Phase Amount
167392
Total Phase Actual Spending Amount
160128
Dsf Number S
DSF0001034906, DSF0001009409, DSF0001083827
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-RESPONSE ACTION NEEDED DUE TO OBSERVED DAMAGE FROM PS 3235 - ROOM 235 - 9X9 FT 1007A - TOILET C
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/15/2025
Project Phase Planned End Date
IEH
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
94428
Total Phase Actual Spending Amount
2436
Dsf Number S
SCA0000074918
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-AHERA P.S RESPONSE ACTION ABATEMENT ABATE AND REPLACE FLOOR TILES IN ROOMS: 337, 204 AND 335
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/19/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
6/20/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
88941
Total Phase Actual Spending Amount
2450
Dsf Number S
SCA0000075628
15
Project Geographic District : 15 • Project Building Identifier: K001 • Project School Name: P.S. 1 - BROOKLYN
Project Geographic District
15
Project Building Identifier
K001
Project School Name
P.S. 1 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-REMOVE SINK ALONG WITH THE CABINETS. 2' X 3'. 2' HIGH ABATE AND REPLACE FLOORS 20 SQFT. ADDRESS
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
4/27/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/16/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
23981
Total Phase Actual Spending Amount
3003
Dsf Number S
SCA0000075864
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
200000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163523
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: I.S. 2 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
I.S. 2 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY24 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/14/2025
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
352799
Total Phase Actual Spending Amount
342085
Dsf Number S
DSF0001085933
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY24 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
125000
Final Estimate Of Actual Costs Through End Of Phase Amount
125000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001085935
17
Project Geographic District : 17 • Project Building Identifier: K002 • Project School Name: K141 SPED - BROOKLYN
Project Geographic District
17
Project Building Identifier
K002
Project School Name
K141 SPED - BROOKLYN
Project Type
SCA Furniture & Equipment
Project Description
FY24 RESO A MOBILE SCIENCE LABS
Project Phase Name
F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
125000
Final Estimate Of Actual Costs Through End Of Phase Amount
125000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001085934
13
Project Geographic District : 13 • Project Building Identifier: K003 • Project School Name: P.S. 3 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K003
Project School Name
P.S. 3 - BROOKLYN
Project Type
SCA IEH
Project Description
PO18-REMOVE PIPE INSULATION FROM STEAM RETURN LINE LOCATED IN THE FAN RM. #18 SPACE ID# 1018 AREA
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
3/18/2026
Project Phase Planned End Date
IEH
Project Phase Actual End Date
5/7/2026
Project Budget Amount
IEH
Final Estimate Of Actual Costs Through End Of Phase Amount
984
Total Phase Actual Spending Amount
234
Dsf Number S
SCA0000075615
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
CM,Art,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/3/2026
Project Budget Amount
10668320
Final Estimate Of Actual Costs Through End Of Phase Amount
8658596
Total Phase Actual Spending Amount
5436018
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/11/2023
Project Phase Planned End Date
9/3/2026
Project Budget Amount
75678395
Final Estimate Of Actual Costs Through End Of Phase Amount
69272421
Total Phase Actual Spending Amount
63125074
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/16/2022
Project Phase Planned End Date
4/5/2023
Project Phase Actual End Date
4/28/2023
Project Budget Amount
6000930
Final Estimate Of Actual Costs Through End Of Phase Amount
3284084
Total Phase Actual Spending Amount
2746633
Dsf Number S
DSF0000890667
15
Project Geographic District : 15 • Project Building Identifier: K004 • Project School Name: I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Geographic District
15
Project Building Identifier
K004
Project School Name
I.S. @ 4012 FORT HAMILTON PARKWAY - BROOKLYN
Project Type
SCA Capacity
Project Description
NEW SCHOOL
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
6/3/2022
Project Phase Planned End Date
9/15/2022
Project Phase Actual End Date
9/15/2022
Project Budget Amount
1333540
Final Estimate Of Actual Costs Through End Of Phase Amount
918157
Total Phase Actual Spending Amount
918157
Dsf Number S
DSF0000890667
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY26 RESO A TECHNOLOGY UPGRADE
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
500000
Total Phase Actual Spending Amount
500000
Dsf Number S
DSF0001163524
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: K140 SPED - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
K140 SPED - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY26 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
250000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001163525
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY23 RESO A STEM LAB
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/2/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
279578
Dsf Number S
DSF0001035360
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - RESOA
Project Description
FY22 RESO A ROOM CONVERSION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/19/2023
Project Phase Planned End Date
DOER
Project Budget Amount
DOER
Final Estimate Of Actual Costs Through End Of Phase Amount
220310
Total Phase Actual Spending Amount
43958
Dsf Number S
DSF0001034976
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
DEP GREEN INFRASTRUCTURE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/18/2020
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
1021917
Total Phase Actual Spending Amount
460404
Dsf Number S
DSF0000865729
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
Fast Track Projects
Project Description
WINDOWS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/22/2023
Project Phase Planned End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
23798093
Total Phase Actual Spending Amount
21735862
Dsf Number S
DSF0001085193
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
8/8/2022
Project Phase Planned End Date
8/6/2024
Project Budget Amount
1175650
Final Estimate Of Actual Costs Through End Of Phase Amount
1550700
Total Phase Actual Spending Amount
1517671
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
8/8/2022
Project Phase Planned End Date
8/6/2024
Project Budget Amount
18894375
Final Estimate Of Actual Costs Through End Of Phase Amount
17770782
Total Phase Actual Spending Amount
15475135
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
12/10/2020
Project Phase Planned End Date
8/31/2021
Project Phase Actual End Date
8/9/2021
Project Budget Amount
839750
Final Estimate Of Actual Costs Through End Of Phase Amount
907182
Total Phase Actual Spending Amount
869918
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/CLIMATE CONTROL / ELECTRIFICATION/BOILER REMOVAL / LOW VOLTAGE ELECTRICAL SYSTEM / ELECTRICAL SYSTEMS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/17/2020
Project Phase Planned End Date
2/23/2021
Project Phase Actual End Date
12/9/2020
Project Budget Amount
167950
Final Estimate Of Actual Costs Through End Of Phase Amount
222642
Total Phase Actual Spending Amount
208642
Dsf Number S
DSF0000936438, DSF0000961025, DSF0000984743, DSF0000984750
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
6000
Final Estimate Of Actual Costs Through End Of Phase Amount
6000
Total Phase Actual Spending Amount
40
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
88000
Final Estimate Of Actual Costs Through End Of Phase Amount
88000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Design
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
6000
Final Estimate Of Actual Costs Through End Of Phase Amount
6000
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
16
Project Geographic District : 16 • Project Building Identifier: K005 • Project School Name: P.S. 5 - BROOKLYN
Project Geographic District
16
Project Building Identifier
K005
Project School Name
P.S. 5 - BROOKLYN
Project Type
SCA CIP RESOA
Project Description
FY23 RESO A PA SYSTEM UPGRADE
Project Phase Name
Scope
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
0
Final Estimate Of Actual Costs Through End Of Phase Amount
0
Total Phase Actual Spending Amount
0
Dsf Number S
DSF0001035361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
ADA SHELTER COMPLIANCE
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
9/17/2018
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
101671
Total Phase Actual Spending Amount
101671
Dsf Number S
DSF0000865885
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY25 RESO A GYMNASIUM UPGRADE
Project Phase Name
Construction
Project Status Name
Complete
Project Phase Actual Start Date
11/12/2025
Project Phase Planned End Date
FTK
Project Phase Actual End Date
5/10/2026
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
189915
Total Phase Actual Spending Amount
132634
Dsf Number S
DSF0001112512
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
Fast Track Projects
Project Description
FY26 RESO A BATHROOM UPGRADES
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
FTK
Project Phase Planned End Date
FTK
Project Phase Actual End Date
FTK
Project Budget Amount
FTK
Final Estimate Of Actual Costs Through End Of Phase Amount
8781
Total Phase Actual Spending Amount
224
Dsf Number S
DSF0001163526
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/15/2026
Project Phase Planned End Date
5/10/2027
Project Budget Amount
43623
Final Estimate Of Actual Costs Through End Of Phase Amount
20813
Total Phase Actual Spending Amount
20813
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/15/2026
Project Phase Planned End Date
5/10/2027
Project Budget Amount
170056
Final Estimate Of Actual Costs Through End Of Phase Amount
159918
Total Phase Actual Spending Amount
4984
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/13/2025
Project Phase Planned End Date
9/8/2025
Project Phase Actual End Date
8/26/2025
Project Budget Amount
11830
Final Estimate Of Actual Costs Through End Of Phase Amount
8366
Total Phase Actual Spending Amount
8366
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
3/12/2025
Project Phase Planned End Date
7/11/2025
Project Phase Actual End Date
3/13/2025
Project Budget Amount
2958
Final Estimate Of Actual Costs Through End Of Phase Amount
2091
Total Phase Actual Spending Amount
2091
Dsf Number S
DSF0001087361
17
Project Geographic District : 17 • Project Building Identifier: K006 • Project School Name: P.S. 6 - BROOKLYN
Project Geographic District
17
Project Building Identifier
K006
Project School Name
P.S. 6 - BROOKLYN
Project Type
SCA Emergency Response
Project Description
EMERGENCY STABILIZATION
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
2/10/2022
Project Phase Planned End Date
EMER
Project Budget Amount
EMER
Final Estimate Of Actual Costs Through End Of Phase Amount
476741
Total Phase Actual Spending Amount
449900
Dsf Number S
SCA0000070859
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: P.S. 7 - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
P.S. 7 - BROOKLYN
Project Type
DIIT - RESOA
Project Description
FY18 RESO A IP SECURITY CAMERAS
Project Phase Name
Purch & Install
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
DIIR
Final Estimate Of Actual Costs Through End Of Phase Amount
345611
Total Phase Actual Spending Amount
345611
Dsf Number S
DSF0000866412
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
4/16/2025
Project Phase Planned End Date
3/11/2026
Project Budget Amount
112578
Final Estimate Of Actual Costs Through End Of Phase Amount
107117
Total Phase Actual Spending Amount
105109
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/16/2025
Project Phase Planned End Date
3/11/2026
Project Budget Amount
161472
Final Estimate Of Actual Costs Through End Of Phase Amount
146045
Total Phase Actual Spending Amount
122798
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
3/20/2024
Project Phase Planned End Date
9/13/2024
Project Phase Actual End Date
7/16/2024
Project Budget Amount
12528
Final Estimate Of Actual Costs Through End Of Phase Amount
10286
Total Phase Actual Spending Amount
10286
Dsf Number S
DSF0001087362
19
Project Geographic District : 19 • Project Building Identifier: K007 • Project School Name: K004 SPED - BROOKLYN
Project Geographic District
19
Project Building Identifier
K007
Project School Name
K004 SPED - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
1/11/2024
Project Phase Planned End Date
5/10/2024
Project Phase Actual End Date
1/11/2024
Project Budget Amount
2784
Final Estimate Of Actual Costs Through End Of Phase Amount
2571
Total Phase Actual Spending Amount
2571
Dsf Number S
DSF0001087362
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
CM,F&E
Project Status Name
In-Progress
Project Phase Actual Start Date
6/17/2026
Project Phase Planned End Date
5/12/2027
Project Budget Amount
49826
Final Estimate Of Actual Costs Through End Of Phase Amount
23811
Total Phase Actual Spending Amount
5467
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
6/17/2026
Project Phase Planned End Date
5/12/2027
Project Budget Amount
194235
Final Estimate Of Actual Costs Through End Of Phase Amount
184268
Total Phase Actual Spending Amount
5930
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Design
Project Status Name
Complete
Project Phase Actual Start Date
9/10/2025
Project Phase Planned End Date
3/11/2026
Project Phase Actual End Date
3/9/2026
Project Budget Amount
13512
Final Estimate Of Actual Costs Through End Of Phase Amount
13437
Total Phase Actual Spending Amount
13437
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K008 • Project School Name: P.S. 8 - BROOKLYN
Project Geographic District
13
Project Building Identifier
K008
Project School Name
P.S. 8 - BROOKLYN
Project Type
SCA CIP
Project Description
IPDVS INSTALLATIONS
Project Phase Name
Scope
Project Status Name
Complete
Project Phase Actual Start Date
9/3/2025
Project Phase Planned End Date
1/6/2026
Project Phase Actual End Date
9/10/2025
Project Budget Amount
3378
Final Estimate Of Actual Costs Through End Of Phase Amount
3360
Total Phase Actual Spending Amount
3360
Dsf Number S
DSF0001087363
13
Project Geographic District : 13 • Project Building Identifier: K009 • Project School Name: PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Geographic District
13
Project Building Identifier
K009
Project School Name
PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Type
DOE - Skilled Trades
Project Description
WATER HEATERS
Project Phase Name
Construction
Project Status Name
In-Progress
Project Phase Actual Start Date
4/4/2017
Project Phase Planned End Date
DOES
Project Budget Amount
DOES
Final Estimate Of Actual Costs Through End Of Phase Amount
30109
Total Phase Actual Spending Amount
17036
Dsf Number S
DSF0000777935
13
Project Geographic District : 13 • Project Building Identifier: K009 • Project School Name: PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Geographic District
13
Project Building Identifier
K009
Project School Name
PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / ELECTRICAL SERVICE UPGRADE / LOW VOLTAGE ELECTRICAL SYSTEMS / ROOFS / WINDOWS / PARAPETS / LIGHTING UPGRADE
Project Phase Name
CM,F&E
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
4702580
Final Estimate Of Actual Costs Through End Of Phase Amount
4702580
Total Phase Actual Spending Amount
274566
Dsf Number S
DSF0001112302, DSF0001112311, DSF0001113808, DSF0001115545, DSF0001114003, DSF0001115546, DSF0001115541
13
Project Geographic District : 13 • Project Building Identifier: K009 • Project School Name: PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Geographic District
13
Project Building Identifier
K009
Project School Name
PUBLIC SCHOOL 9 THE SARAH SMITH GARNET SCHOOL - BROOKLYN
Project Type
SCA CIP
Project Description
ELECTRIFICATION/HEAT PUMP SYSTEMS / ELECTRICAL SERVICE UPGRADE / LOW VOLTAGE ELECTRICAL SYSTEMS / ROOFS / WINDOWS / PARAPETS / LIGHTING UPGRADE
Project Phase Name
Construction
Project Status Name
PNS
Project Phase Actual Start Date
PNS
Project Phase Planned End Date
PNS
Project Phase Actual End Date
PNS
Project Budget Amount
45802133
Final Estimate Of Actual Costs Through End Of Phase Amount
45802133
Total Phase Actual Spending Amount
192358
Dsf Number S
DSF0001112302, DSF0001112311, DSF0001113808, DSF0001115545, DSF0001114003, DSF0001115546, DSF0001115541