Active Projects

List of currently active projects. Project IDs are another way of referring to FMS IDs for an active project.  This project identifier provides a critical way of checking funding and procurement details of City projects.

Please refer to The Mayor’s Office of Operations Capital Project Dashboard to see further project and budget details.

Housing & Development Department of Design and Construction (DDC) Dataset 3ss8-m844 8 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
227DUFFIELD
Project Id: 227DUFFIELD • Description: 227 Duffield St. - Temporary Seal and Stabilization • Client Agency: DCAS
Project Id
227DUFFIELD
Description
227 Duffield St. - Temporary Seal and Stabilization
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2023-02-28T00:00:00.000
Scope
Temporary seal and stabilization of the building per DOB requirements.
Status
Active
70MULBREC
Project Id: 70MULBREC • Description: 70 MULBERRY STREET - RECONSTRUCTION • Client Agency: DCAS
Project Id
70MULBREC
Description
70 MULBERRY STREET - RECONSTRUCTION
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2028-03-22T00:00:00.000
Scope
Exterior will be preserved or reconstructed to retain its characteristics/appearance as a cultural landmark, while reconstructing and modernizing the interior that meets existing tenants needs and latest building codes/standards. Building will have original square footage plus gymnasium/multi-purpose floor. Building must be designed to have but not limited: new central multi-zone HVAC system, new MEP services and distribution, BMS,FA,FP, Security/communication, new chiller/boiler plant in basement, emergency generator, new elevator (two preferably for redundancy), new restrooms, new kitchen for the senior and kitchenettes.
Status
Active
ACEDCA433
Project Id: ACEDCA433 • Client Agency: Cultural Affairs • Division: Public Buildings
Project Id
ACEDCA433
Description
WCS/DCAS ACE Program Round 1, Roof Replacement
Project, Four Buildings - DCLA/DDC CCG
Client Agency
Cultural Affairs
Division
Public Buildings
Phase
4. Construction
Projected Construction
2026-04-28T00:00:00.000
Scope
The ACE Program Bronx Zoo Roof Replacement project will replace the roofing systems for four Bronx Zoo campus buildings: The Aquatic Bird House (5000 square feet, built in1961)
The Wild Asia Comfort Station (2400 square feet, built in 1976)
The African Plains Lion House (2000 square feet, built in 1940)
The Nyala Barn (1800 square feet, built in 1940)
Status
Active
ACEDCA702
Project Id: ACEDCA702 • Description: METS REPLACEMENT OF 7 AIR HANDLING UNITS • Client Agency: Cultural Affairs
Project Id
ACEDCA702
Description
METS REPLACEMENT OF 7 AIR HANDLING UNITS
Client Agency
Cultural Affairs
Division
Public Buildings
Phase
4. Construction
Projected Construction
2023-05-31T00:00:00.000
Scope
The new Air Handlers will be modern state-of-the-art equipment which will improve energy efficiency, improve indoor air quality, and provide a more stable environment for the staff and visitors. With the new equipment and controls, the desired temperature and humidity conditions will be more consistent, reliable and have unoccupied mode ability.
Status
Active
ACEDCA703
Project Id: ACEDCA703 • Description: AMNH – ACE Central Plant Upgrade • Client Agency: Cultural Affairs
Project Id
ACEDCA703
Description
AMNH – ACE Central Plant Upgrade
Client Agency
Cultural Affairs
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2022-12-30T00:00:00.000
Scope
The Museum’s Central Plant provides heating and cooling for a majority of the campus 365 days a year. Two of the existing four chillers and two cooling towers, installed in 1997 City-funded Pass-Through PVC034-S, are degraded and have exceeded their useful lives. The Museum proposes to demolish and replace two chillers that serve 68% of the Museum’s complex and to demolish and replace two cooling towers (CTs) that serve the existing complex. Currently, approximately 68% of the Museum utilizes chilled water for cooling needs.
Status
Active
BBJ-KDSS
Project Id: BBJ-KDSS • Description: Dismantal of Brooklyn Detention Facility • Client Agency: Corrections
Project Id
BBJ-KDSS
Description
Dismantal of Brooklyn Detention Facility
Client Agency
Corrections
Division
Public Buildings
Phase
2. Design
Projected Construction
2023-08-24T00:00:00.000
Scope
BBJ Dismantle of existing Brooklyn Detention Center and construction of Swing Space/interim Sallyport
Status
Active
BBJ-QTWM
Project Id: BBJ-QTWM • Description: Installation of 48” Steel Trunk Water Main • Client Agency: Environmental Protection
Project Id
BBJ-QTWM
Description
Installation of 48” Steel Trunk Water Main
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2023-09-24T00:00:00.000
Scope
Installation of 48” Steel Trunk Water Main for BBJ-Q.
126 St. between Union Turnpike and 82nd Ave.
132 St. between Union Turnpike and 82nd Ave.
Status
Active
BED776
Project Id: BED776 • Description: WM REPLMT EAST NEW YORK AVE • Client Agency: Environmental Protection
Project Id
BED776
Description
WM REPLMT EAST NEW YORK AVE
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2024-09-09T00:00:00.000
Scope
Trunk Water Main replacement in:

1. East New York Avenue between Howard Avenue and Pacific Street.
2. Jamaica Avenue between Herkimer Street and Vermont Street.
3. Atlantic Avenue between Van Sinderen Avenue and Pennsylvania Avenue.
Status
Active
BED777
Project Id: BED777 • Description: TRUNK & DIST. WM REPLMT IN LEONARD STREET • Client Agency: Environmental Protection
Project Id
BED777
Description
TRUNK & DIST. WM REPLMT IN LEONARD STREET
Client Agency
Environmental Protection
Division
Infrastructure
Phase
5. Close-Out
Projected Construction
2020-09-09T00:00:00.000
Scope
Trunk and distribution water mains replacement in:

Leonard Street between Driggs Avenue and Maujer Street

WM-6
1. Leonard Street between Driggs Avenue and Maujer Street
2. Intersection of Leonard Street and Maujer Street

WM-1
1. Leonard Street between Driggs Avenue and Maujer Street including all intersections.

Sanitary Sewer in:
1. Leonard Street between Driggs Ave and Manhattan Ave

Combined Sewers in:
1. Leonard Street between Engert Avenue and Bayard Street
2. Leonard Street between Richardson Street and Meeker Avenue
3. Along Skillman Avenue at Leonard Street
4. Metropolitan Avenue between Leonard Street and Manhattan Avenue
5. Leonard Street betweeb Devoe Street and Ainsile Street
Status
Active
BED778A
Project Id: BED778A • Description: REPLACEMENT OF TRUNK WATER MAINS IN ATLANTIC AVE • Client Agency: Environmental Protection
Project Id
BED778A
Description
REPLACEMENT OF TRUNK WATER MAINS IN ATLANTIC AVE
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2023-05-31T00:00:00.000
Scope
Trunk and Distribution Water Mains Replacement in Atlantic Avenue between Carlton Avenue and Portland Avenue in the Borough of Brooklyn.

Water Main (WM-6) in:
1. Atlantic Avenue from Carlton Avenue to South Portland Avenue.
2. Intersection of Atlantic Avenue and Carlton Avenue.

Water Main(WM -1) in:
1. Atlantic Avenue(SS) from Carlton Avenue to South Portland Avenue
2. Intersection of Atlantic Avenue and Carlton Avenue
3. Intersection of Atlantic Avenue and Cumberland Street.
Status
Active
BED798
Project Id: BED798 • Description: REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE • Client Agency: Environmental Protection
Project Id
BED798
Description
REPLACEMENT OF 72" TRUNK WM IN FLATBUSH AVE
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2023-09-29T00:00:00.000
Scope
72" Trunk Water Main and Combined Sewer Replacement in Flatbush Ave. between Sterling Pl. and 8th Ave., etc., Borough of Brooklyn.

WM-6 in:
1. Flatbush Ave. between Park Place and 8th Ave
2. 8th Ave. between Flatbush Ave. and Lincoln Place
3. Park Place between 5th Ave. and 6th Avenue
4. St. Johns Place between 5th Ave. and 8th Ave
5. 6th Avenue between Park Place and Union Street

WM-1 in:
1. Flatbush Avenue between Park Place and 8th Avenue

Combined sewer in:
1. Park Place between 5th Ave. and 6th Avenue
2. St. Johns Place between 5th Ave. and Flatbush Ave.
3. 6th Avenue between Park Place and Union Street
4. 8th Ave. between St. John's Place and Lincoln Place

Additional scope:
Reconstruction of triangle at 8th Avenue and Flatbush Avenue removed from HWK300-01 and to be constructed under the BED-798.
Status
Active
BED819
Project Id: BED819 • Description: WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN • Client Agency: Environmental Protection
Project Id
BED819
Description
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2024-09-17T00:00:00.000
Scope
WATERMAIN REPLACEMENT IN ORIENTAL BLVD, BROOKLYN
Status
Active
BED-827
Project Id: BED-827 • Description: REGULAR CHAMBER ROOF REPLACEMENT • Client Agency: Environmental Protection
Project Id
BED-827
Description
REGULAR CHAMBER ROOF REPLACEMENT
Client Agency
Environmental Protection
Division
Infrastructure
Phase
3. Construction Procurement
Projected Construction
2024-08-14T00:00:00.000
Scope
REGULATOR CHAMBER ROOF REPLACEMENTS: BROOKLYN (5), BRONX (1). FIVE REGULATOR LOCATIONS IN BROOKLYN AND ONE REGULATOR LOCATION IN THE BRONX WILL HAVE THEIR EXISTING CONCRETE SLAB ROOFS REMOVED AND REPLACED WITH NEWLY POURED ROOFS SO THAT ACCESS COVERS ARE APPROPRIATELY CENTERED OVER DISTRIBUTION ASSETS. THIS WORK WILL INCLUDE THE DESIGN AND CONSTRUCTION OF STRUCTURAL STEEL SUPPORTING THE CONCRETE ROOFS.
Status
Active
BEDA003
Project Id: BEDA003 • Description: ACCELERATED DIST WATER MAIN REPLACEMENT, BK • Client Agency: Environmental Protection
Project Id
BEDA003
Description
ACCELERATED DIST WATER MAIN REPLACEMENT, BK
Client Agency
Environmental Protection
Division
Infrastructure
Phase
5. Close-Out
Projected Construction
2022-09-21T00:00:00.000
Scope
ACCELERATED DISTRIBUTION WATER MAIN REPLACEMENT AND SEWER REHABILITATION/REPLACEMENT, BROOKLYN
Status
Active
BLCOMPLNT
Project Id: BLCOMPLNT • Description: Standard Ped Ramp Upgrades and Installs - Citywide • Client Agency: Transportation
Project Id
BLCOMPLNT
Description
Standard Ped Ramp Upgrades and Installs - Citywide
Client Agency
Transportation
Division
Infrastructure
Phase
3. Construction Procurement
Projected Construction
2025-07-15T00:00:00.000
Scope
The scope includes rehabilitation and installation of pedestrian ramps (repair, upgrade and install to the maximum extent feasible under Federal ADA 2010 specifications and PROWAG guidelines as outlined in the Minimum Design Requirements section of this document) in Bronx, Brooklyn, Manhattan, Queens and Staten Island.
Status
Active
C75EWGRVC
Project Id: C75EWGRVC • Description: Renovation of George R Vierno Center (GRVC) at Rikers Island • Client Agency: Corrections
Project Id
C75EWGRVC
Description
Renovation of George R Vierno Center (GRVC) at Rikers Island
Client Agency
Corrections
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2024-07-17T00:00:00.000
Scope
GRVC (George R. Vierno Center). Housing UNIT 6A conversion from individual cells to incentive-based program areas. Selective Demolition:
Housing Cells
6” CMU cell walls (8,145 SF)
(16) 6.75’d x 7.66’w x 9’h = 7,445.5 SF
(9) 6.75’d X 11.5’w x 9’h = 700 SF
(9) Detention Doors 12 or 14 Gage Steel with vision panels and food
service slots
(9) 12 gage Door Frames with Control panels
(48) Stainless steel wall hung detention WCs
(48) Stainless Steel wall hung detention Lavatories
(48) stainless steel recessed wall shelves
(48) stainless steel surface mounted mirrors
Removal of 48 steel detention beds (bolted to floor
Status
Active
C75EWRNIC
Project Id: C75EWRNIC • Description: Renovation of North Infirmary Command (NIC) at Rikers Island • Client Agency: Corrections
Project Id
C75EWRNIC
Description
Renovation of North Infirmary Command (NIC) at Rikers Island
Client Agency
Corrections
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2023-02-28T00:00:00.000
Scope
Renovation of existing locker rooms in dormitory #4, (cheveron A and B). Work include floor finishes , hvac, plumbing fixtures and lighting.
Status
Active
CJCREN
Project Id: CJCREN • Description: Crossroads Juvenile Center • Client Agency: Children Services
Project Id
CJCREN
Description
Crossroads Juvenile Center
Client Agency
Children Services
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2019-03-01T00:00:00.000
Scope
Major renovation and upgrade of all building systems
Status
Active
CO272DW2
Project Id: CO272DW2 • Description: BROOKLYN APPELLATE DIVISION SUPREME COURT - PARKING RECONSTRUCTION AND SITE WORK • Client Agency: DCAS
Project Id
CO272DW2
Description
BROOKLYN APPELLATE DIVISION SUPREME COURT - PARKING RECONSTRUCTION AND SITE WORK
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2025-06-27T00:00:00.000
Scope
• Removal and replacement of existing driveway and court yard pavement.
• Excavate and replace existing drain pipes and catch basins.
• Fill and compact entire sub-base.
• Pour new asphalt, provide new curb.
• Replace existing lights.
• Connect main sewer drain.
• Install new sidewalk and new security gate.
Status
Active
CO272ELC2
Project Id: CO272ELC2 • Description: 45 MONROE PL - ELECTRICAL / FA UPGRADE • Client Agency: DCAS
Project Id
CO272ELC2
Description
45 MONROE PL - ELECTRICAL / FA UPGRADE
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2023-04-02T00:00:00.000
Scope
Replace and upgrade the switchgear and the electrical distribution panels.
Replace feeder/ riser wiring.
Provide a new Emergency Generator for all Life Safety Systems.
Provide a new Fire Alarm System to replace existing.
Comply with new 2014 NYC Electrical Code.
Status
Active
CO272ELV2
Project Id: CO272ELV2 • Description: 45 MONROE PL - ELEVATOR Modernization • Client Agency: DCAS
Project Id
CO272ELV2
Description
45 MONROE PL - ELEVATOR Modernization
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2019-06-20T00:00:00.000
Scope
Modernization of the two elevators at the Appelate Court in Brooklyn.
Location - 45 Monroe Place, Brooklyn NY.
All major components will be replaced both in kind and with technology upgrades: for example, existing DC geared traction hoist machines will be replaced with AC gearless VVVF - AC drives and corresponding controllers.
Status
Active
CO277ELV2
Project Id: CO277ELV2 • Description: 25-10 COURT HOUSE SQ.- ELEVATORS • Client Agency: DCAS
Project Id
CO277ELV2
Description
25-10 COURT HOUSE SQ.- ELEVATORS
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2021-02-05T00:00:00.000
Scope
The project provides for a comprehensive renovation of the facility's two elevators.
Status
Active
CO277FA
Project Id: CO277FA • Description: 126 Long Island City Courthouse: Fire Alarms • Client Agency: DCAS
Project Id
CO277FA
Description
126 Long Island City Courthouse: Fire Alarms
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2027-06-24T00:00:00.000
Scope
CO277FA Long Island Courthouse Fire Alarm upgrade
Status
Active
CO278EXT2
Project Id: CO278EXT2 • Description: Brooklyn Supreme Court Facade Rehabilitation • Client Agency: DCAS
Project Id
CO278EXT2
Description
Brooklyn Supreme Court Facade Rehabilitation
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2026-07-31T00:00:00.000
Scope
Undertake a comprehensible restoration of the façade and its elements as well as removing and replacing sections of the roof parapet and associated flashing. Secure loose parapets stone coping and repointing parapet. Reinforced and/or replace damaged and/or displaced stone panels. Reinforcement and/or replacement of deteriorated/rusty structural steel behind the façade as well as sagging steel above wall openings, seal windows and adjuncts openings. Rehabilitation of large section of deteriorate masonry as well as cleaning of the stone façade and aluminum fenestration to protect pedestrians and restore the building appearance to an esthetically acceptable state.
Status
Active
CO278FA3
Project Id: CO278FA3 • Description: Brooklyn Supreme court 360 Adams Fire Alarms • Client Agency: DCAS
Project Id
CO278FA3
Description
Brooklyn Supreme court 360 Adams Fire Alarms
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2031-06-30T00:00:00.000
Scope
New addressable non-proprietary Fire Detection & Alarm system in full compliance with current Building, Electrical & Fire Protection Codes of the City of New York as mandated by Local Law #5 of 1973 and its latest amendments.
New sprinkler system prior to 2019 as mandated by Local Law 26.
Status
Active
CO281TOIL
Project Id: CO281TOIL • Description: Central Courts Building:120 Schermerhorn St. • Client Agency: DCAS
Project Id
CO281TOIL
Description
Central Courts Building:120 Schermerhorn St.
Client Agency
DCAS
Division
Public Buildings
Phase
4. Construction
Projected Construction
2024-01-23T00:00:00.000
Scope
ADA & Code Compliant Public Restroom/ Holding Cell Toilet Upgrade.
Status
Active
CO283FIRE
Project Id: CO283FIRE • Description: 100 Centre Street Fire Alarm Upgrade • Client Agency: DCAS
Project Id
CO283FIRE
Description
100 Centre Street Fire Alarm Upgrade
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2016-01-29T00:00:00.000
Scope
Installation of a new fire alarm system for 100 Centre Street which will include new data gathering panels at various floors and all other necessary conduit, wires, speakers, strobes, combos, etc to make a new system. Old system will be removed. Components will also involve the DA wing and the Department of Corrections.
Status
Active
CO283SID2
Project Id: CO283SID2 • Description: 100 Centre Sidewalk Stabilization and Ramps • Client Agency: DCAS
Project Id
CO283SID2
Description
100 Centre Sidewalk Stabilization and Ramps
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2019-06-28T00:00:00.000
Scope
Sidewalk replacement and handicap accessibility. Project involves replacement of the sidewalk, restoration of the entrances to the building, new handicap ramps on the North and Side entrances to the building on Centre Street.
Status
Active
CO283TOIL
Project Id: CO283TOIL • Description: Criminal Courthouse: 100 Centre Street • Client Agency: DCAS
Project Id
CO283TOIL
Description
Criminal Courthouse: 100 Centre Street
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2026-03-07T00:00:00.000
Scope
ADA & Code Compliant Public Restroom/Holding Cell Toilet Upgrade/Renovations
Status
Active
CO283WT
Project Id: CO283WT • Description: 100 CENTRE STREET - WATER TANK • Client Agency: DCAS
Project Id
CO283WT
Description
100 CENTRE STREET - WATER TANK
Client Agency
DCAS
Division
Public Buildings
Phase
3. Construction Procurement
Projected Construction
2025-04-13T00:00:00.000
Scope
Replacement of existing house tanks and associated structural support for the water tanks located on the 20th flr. The Project includes but it is not limited to: Selective demolition of existing steel tanks of approx. 18,000 gallons and auxiliaries as well as the existing structural supports; crane to hoist the new tanks, provide new structural supports, installation of new tanks, provide new heat trace and insulation as required; performing all associated electrical, controls, plumbing and GC work.
Status
Active
CO285FIRE
Project Id: CO285FIRE • Description: Family Crthouse:60 Lafayette St NY.FireAlarmUpgrad • Client Agency: DCAS
Project Id
CO285FIRE
Description
Family Crthouse:60 Lafayette St NY.FireAlarmUpgrad
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2027-06-21T00:00:00.000
Scope
Upgrade of the Fire Alarm system
Status
Active
CO290BCHJ
Project Id: CO290BCHJ • Description: BCHJ-Post Construction Work • Client Agency: DCAS
Project Id
CO290BCHJ
Description
BCHJ-Post Construction Work
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2021-12-15T00:00:00.000
Scope
Remediation work at the Bronx County Hall of Justice as indicated in the Project Objectives, Exhibit C. Work includes HVAC, roof leaks, glass breakage, intumescent paint, plumbing and audio/visual.
Status
Active
CO290BCHJ-2
Project Id: CO290BCHJ-2 • Description: BRONX HALL OF JUSTICE POST CONSTRUCTION • Client Agency: DCAS
Project Id
CO290BCHJ-2
Description
BRONX HALL OF JUSTICE POST CONSTRUCTION
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2022-12-30T00:00:00.000
Scope
BRONX HALL OF JUSTICE POST CONSTRUCTION BID PACKAGE 2-
HVAC AIRFLOW ISSUES
This scope includes the installation of a new transfer air fan and associated ductwork with sound attenuation on the inlet and outlet of a fan serving the Judge’s Lounge located at the 7th Floor. New transfer air ducts are being installed on floors 2, 7 & 8 to assist in the proper function of the return air system. Additional fan coil units are being installed to serve several rooms on the 8th floor & the 7th floor elevator lobby.

ENGINATOR EXHAUST HEAT
This scope involves a means of venting excessive heat that builds up in a shaft way that houses the enginator exhaust pipe that begins in lower level 2 up and out through the roof of the building. The heat emanates through the shaft way walls into the building. This will be accomplished by installing a new exhaust fan and a makeup air fan that pumps outside air into the shaft way.

CURTAINWALL SHADOW BOX HEAT TRANSFER
Original design created conditions where curtain wall mullions heated to temperatures in excess of 110 F. This scope of works involves installing new metal stud with sheetrock finishes over interior curtain wall mullions. Affected locations are portions of the 2nd floor east side exposure.

WATER PENETRATION THROUGH UNDERGROUND CONDUITS
An existing underground conduit experienced water infiltration which caused those conductors to fail. Those conductors are going to be removed and the conduit abandoned. A new above ground path has been designed for the new feeder.

INTERIOR GLASS REPLACEMENT
Replace 4 sections of glazing at Stair A and 1 section at Stair B.

CONDENSER WATER SYSTEM WITH THREE ROOF TOP DRY COOLERS
Furnish and install a complete new A/C condenser cooling glycol system that includes roof top dry coolers and associated piping. This new system will serve chilled water A/C units in IT closets and elevator machine rooms throughout the building.
Status
Active
CO293LL11
Project Id: CO293LL11 • Description: 851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11 • Client Agency: DCAS
Project Id
CO293LL11
Description
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2027-02-28T00:00:00.000
Scope
851 GRAND CONCOURSE - FACADE REPAIRS LOCAL LAW 11
Status
Active
CO295EV
Project Id: CO295EV • Description: 1118 GRAND CONCOURSE - ELEVATORS • Client Agency: DCAS
Project Id
CO295EV
Description
1118 GRAND CONCOURSE - ELEVATORS
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2026-10-22T00:00:00.000
Scope
1118 GRAND CONCOURSE - ELEVATORS
Status
Active
CO296RF
Project Id: CO296RF • Description: 125-01 QUEENS BLVD.- ROOF • Client Agency: DCAS
Project Id
CO296RF
Description
125-01 QUEENS BLVD.- ROOF
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2026-08-22T00:00:00.000
Scope
Roof Replacement
Status
Active
CO299EXT2
Project Id: CO299EXT2 • Description: 89-17 SUTPHIN BLVD.- EXTERIOR • Client Agency: DCAS
Project Id
CO299EXT2
Description
89-17 SUTPHIN BLVD.- EXTERIOR
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2027-11-03T00:00:00.000
Scope
89-17 SUTPHIN BLVD.- PLAZA/SIDEWALK RECONSTRUCTION
Status
Active
CO299FIRE
Project Id: CO299FIRE • Description: Civil Courthouse:89-17 Sutphin BLVD,NY.FireAlarmUp • Client Agency: DCAS
Project Id
CO299FIRE
Description
Civil Courthouse:89-17 Sutphin BLVD,NY.FireAlarmUp
Client Agency
DCAS
Division
Public Buildings
Phase
3. Construction Procurement
Projected Construction
2026-12-29T00:00:00.000
Scope
89-17 Sutphin Blvd Fire alarm replacement
Status
Active
CO301LL
Project Id: CO301LL • Description: 130 STUYVESANT PLACE EXTERIOR REHAB, DESIGN PHASE • Client Agency: DCAS
Project Id
CO301LL
Description
130 STUYVESANT PLACE EXTERIOR REHAB, DESIGN PHASE
Client Agency
DCAS
Division
Public Buildings
Phase
4. Construction
Projected Construction
2024-04-13T00:00:00.000
Scope
The scope of this project is to reconstruct the masonry walls at the south façade and bulkhead, replacement of the roofs at each level and related work required at the roof parapets, copings and railings.
Status
Active
CO301PD
Project Id: CO301PD • Description: 130 Stuyvesant Pl. - Parking Garage Deck • Client Agency: DCAS
Project Id
CO301PD
Description
130 Stuyvesant Pl. - Parking Garage Deck
Client Agency
DCAS
Division
Public Buildings
Phase
4. Construction
Projected Construction
2024-04-13T00:00:00.000
Scope
The scope of this project is to renovate the surface deck of the parking garage attached to the Mark A. Costantino Judicial Center. The project scope includes replacement of the top deck waterproofing membrane and wear surfacing, the replacement of flashing at all mechanical penetrations, and the replacement of the parking surface on-grade continuous with the top parking deck. Also included will be new parking deck drains, new surface lighting, installation of automatic pop-up vehicle access gates and modification of vertical access to the building entrance from the parking deck for ADA accessibility will be part of this project.
Status
Active
CO302ST
Project Id: CO302ST • Description: 18 RICHMOND TERRACE - EXTERIOR STEPS RECONSTRUCTI • Client Agency: DCAS
Project Id
CO302ST
Description
18 RICHMOND TERRACE - EXTERIOR STEPS RECONSTRUCTI
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2023-07-31T00:00:00.000
Scope
18 RICHMOND TERRACE - RECONSTRUCTION EXTERIOR STEPS TO REMOVE ALL HAZARDOUS CONDITIONS
Status
Active
CO304REHB
Project Id: CO304REHB • Description: 60 CENTRE ST. - RECONSTRUCTION • Client Agency: DCAS
Project Id
CO304REHB
Description
60 CENTRE ST. - RECONSTRUCTION
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2028-08-01T00:00:00.000
Scope
60 CENTRE - RECONSTRUCTION OF BUILDING - BASEMENT, ROOF AND FACADE
Status
Active
CO305REHB
Project Id: CO305REHB • Description: Midtown Community Court Rehabilitation • Client Agency: DCAS
Project Id
CO305REHB
Description
Midtown Community Court Rehabilitation
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2016-12-07T00:00:00.000
Scope
Midtown Community Court & theater, built in 1865 and designated as a New York Historic Landmark, is approximately 25,000 square feet and comprises of a sub-cellar and cellar, a mezzanine level, and six floors. The general scope of work involves the demolition of an existing exterior stair, masonry wall with its foundation in the rear courtyard to be replaced with an new two hours fire resistive curtain wall/foundation addition which provides extra cellar space for new infrastructure equipment, a large conference room on the first floor, and an enclosed new egress stairwell from the sub cellar to the 6th floor. As part of the building’s envelope upgrade, the scope will include the rehabilitation of the landmark front façade, east & west masonry walls to receive stucco, new windows, new roofing with a major skylight restoration. In addition to the scope of work, the building will receive infrastructure upgrade affecting the mechanical, heating, cooling, plumbing, sprinkler, fire alarm, electrical and lighting system for the building. To monitor the efficient of some of these new systems, a Building Management System will be included in the scope of work. As for interior scope of work, upgrade public restrooms in floors 1thur 6 to incorporate ADA compliance & new restroom design, built interior walls to modify existing wall layout to incorporate separate or combine systems in one location, and built an enclosed north & south shaft walls to incorporate new mechanical supply & return ducts to the roof. Replace existing ceiling with new non-rated & fire rated ceiling thru out. Restore/rebuild and add new elevator’s shaft walls to modernized and install two new elevators.
Status
Active
CO306EXT2
Project Id: CO306EXT2 • Description: 170 East 121 Street - Harlem Courthouse Facade • Client Agency: DCAS
Project Id
CO306EXT2
Description
170 East 121 Street - Harlem Courthouse Facade
Client Agency
DCAS
Division
Public Buildings
Phase
2. Design
Projected Construction
2027-08-02T00:00:00.000
Scope
The building's facade must be repaired to eliminate leaks.
Status
Active
CO80ROOF2
Project Id: CO80ROOF2 • Description: 27 MADISON AVE - ROOF & MISC. OPERATIONS SPACES UP • Client Agency: DCAS
Project Id
CO80ROOF2
Description
27 MADISON AVE - ROOF & MISC. OPERATIONS SPACES UP
Client Agency
DCAS
Division
Public Buildings
Phase
5. Close-Out
Projected Construction
2019-06-11T00:00:00.000
Scope
The project involves renovation/alterations work of the Appellate Court building. The work includes demolition, concrete , caulking , marble repairs ,waterproofing,roofing, mechanical, plumbing electrical/lighting and mural rehabilitation .
Status
Active
CONISPH04
Project Id: CONISPH04 • Description: SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4 • Client Agency: Environmental Protection
Project Id
CONISPH04
Description
SAN & STRM SEWER, WM IN CONEY ISLAND AREA, PH 4
Client Agency
Environmental Protection
Division
Infrastructure
Phase
2. Design
Projected Construction
2028-06-28T00:00:00.000
Scope
INSTALLATION OF NEW TRUNK WATER MAINS AND STORM SEWERS AND REPLACEMENT OF DISTRIBUTION WATER MAINS IN NEPTUNE AVENUE BETWEEN W 8TH/12TH STREET AND OCEAN PARKWAY IN THE BOROUGH OF BROOKLYN. TRUNK WATER MAIN INSTALLATION IS IN ACCORDANCE WITH TRUNK MAIN MASTER PLAN. SEWER INSTALLATION IS PER PRELIMINARY AMENDED DRAINAGE PLAN.
Status
Active
CONISPH2B
Project Id: CONISPH2B • Description: STM, SAN SEWERS & WM IN CONEY ISLAND AREA-PH2B, BK • Client Agency: Environmental Protection
Project Id
CONISPH2B
Description
STM, SAN SEWERS & WM IN CONEY ISLAND AREA-PH2B, BK
Client Agency
Environmental Protection
Division
Infrastructure
Phase
5. Close-Out
Projected Construction
2021-12-23T00:00:00.000
Scope
Storm and Sanitary sewer, Trunk and distribution water main in Coney Island area, Borough of Brooklyn Phase-2B

Storm Sewer
1-Neptune Ave. b/t Stillwell Ave. and West 12th St. (both North & South side)
2-Stillwell Ave. b/t Coney Island Creek and Surf Ave.
3-Outfall at West 12th St.and Neptune Ave. to Coney Is Land Creek

Sanitary Sewer
1-Stillwell Ave. b/t Coney Island Creek to Surf Ave.
2-Neptune Ave. b/t Stillwell Ave. and West 12th St.(both North side and South side)

Watermain
1-Neptune Ave b/t Stillwell Ave. and W. 12th St.
2-Stillwell Ave. b/t Surf Ave. and Coney Island Creek
Status
Active
CONISPH3A
Project Id: CONISPH3A • Description: STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK • Client Agency: Environmental Protection
Project Id
CONISPH3A
Description
STM, SAN SEWERS & WM IN CONEY ISLAND AREA, PH3A,BK
Client Agency
Environmental Protection
Division
Infrastructure
Phase
4. Construction
Projected Construction
2023-11-27T00:00:00.000
Scope
Storm and Sanitary sewer, Trunk and distribution water main in Coney Island area, Borough of Brooklyn

Storm Sewer
1-West 16 St. b/t Surf Ave. and Hart Pl.
2-Surf Ave b/t West 12 St. and West 17 St.
3-Mermaid Ave b/t W 16 St. and Stillwell Ave.
4.-Neptune Ave b/t W 17 St. and Stillwell Ave.
5- Hart Pl. b/t Cropsey Ave and W 15 St.

Sanitary Sewer
1-West 16 St. b/t Surf Ave and Mermaid Ave.
2-West 16 St. b/t Mermaid Ave. and Hart Pl (both East and West side of W 16 St)
3-Surf Ave b/t West 12 St. and West 17 St. (both north and south side of Surf Ave)
4-Mermaid Ave b/t W 17 St. and Stillwell Ave.
5.-Neptune Ave b/t W 17 St. and W 15 St. (both north and south side of Neptune Ave)
6- Hart Pl. b/t W 16 St. and W 15 St. (North Side)
7.-Hart Pl. b/t Cropsey Ave and W 16 St.(both north and south sides)

Watermain (WM-6)
1-Neptune Ave b/t Stillwell Ave. and W 17 St.
2- Surf Ave b/t W 17 St and W 12 St

Water Main (WM-1)
1-Neptune Ave b/t Stillwell Ave. and W 17 St.
2-Mermaid Ave b/t Stillwell Ave. and W 17 St.
3- Surf Ave b/t W 17 St and Stillwell Ave (north and south sides of the strret)
4- Hart Pl. b/t W 16 St. and W 15 St.
5 - W 16 St b/t Surf Ave & Hart Pl.
Status
Active
CRO-AGS
Project Id: CRO-AGS • Description: CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING • Client Agency: Environmental Protection
Project Id
CRO-AGS
Description
CROTON ABOVE GROUND STRUCTURE AND LANDSCAPING
Client Agency
Environmental Protection
Division
Public Buildings
Phase
4. Construction
Projected Construction
2023-12-15T00:00:00.000
Scope
The new Mosholu Golf Course Club House, together with fifty-five Driving Range Tee Boxes and ten-acres of re-landscaping comprise the phase IV and final of the vast DEP Croton Water Treatment Plant project, currently under construction in Van Cortlandt Park in the Bronx. Through a multifunctional design strategy the project reinstates the pre-existing golf program and facility, creates civic space for community use and ensures security for a multi-billion dollar public works facility.
Status
Active
CS-NC-BAF
Project Id: CS-NC-BAF • Description: Design and Construction of Borden Ave PS Force Main. • Client Agency: Environmental Protection
Project Id
CS-NC-BAF
Description
Design and Construction of Borden Ave PS Force Main.
Client Agency
Environmental Protection
Division
Infrastructure
Phase
2. Design
Projected Construction
2028-06-07T00:00:00.000
Scope
DDC will be responsible for the design and construction of the following four major components which are shown in the following sketch:
• A new diversion chamber with a tide gate constructed on private property between the existing regulator/bending weir and the existing BB-026 outfall.
• Approximately 2,800 linear feet (LF), 42 inch diameter gravity sewer from the new diversion chamber to the BAPS underneath 30th Street (avoiding the unmapped 29th Street).
• Approximately 4,350 LF, 36 inch diameter force main from the BAPS to a location just upstream of the Kent Avenue Gate Structure. (The preferred route as well as an alternative route for the force main are shown in the attached sketch)
• Approximately 530 LF, 14 inch diameter force main, from the BAPS to the existing Bowery Bay interceptor. This will be in parallel to the existing dry weather force main.
Status
Active