Title
Crispus Attucks Playground Reconstruction
Summary
This project will reconstruct the playground, handball courts, basketball courts, and entry plaza at Crispus Attucks Playground.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-03-01T00:00:00.000
Designprojectedcompletion
2012-12-01T00:00:00.000
Designadjustedcompletion
2013-03-01T00:00:00.000
Designactualcompletion
2014-08-01T00:00:00.000
Procurementstart
2014-08-01T00:00:00.000
Procurementprojectedcompletion
2015-05-01T00:00:00.000
Procurementadjustedcompletion
2015-09-01T00:00:00.000
Procurementactualcompletion
2015-07-01T00:00:00.000
Constructionstart
2015-10-01T00:00:00.000
Constructionprojectedcom
2017-01-01T00:00:00.000
Constructionadjustedcompletion
2017-06-01T00:00:00.000
Constructionactualcompletion
2017-04-01T00:00:00.000
Projectliaison
James Morris
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
City Council
Name
Classon Avenue between Fulton Street and Lefferts Place