Title
Elizabeth H. Berger Plaza Construction
Summary
This project will construct Elizabeth H. Berger Plaza, closing the slip road between two smaller parks to create one larger plaza with plantings, a lawn mound, and seating.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2012-10-01T00:00:00.000
Designprojectedcompletion
2015-09-01T00:00:00.000
Designadjustedcompletion
2018-03-01T00:00:00.000
Designactualcompletion
2018-03-01T00:00:00.000
Procurementstart
2018-03-01T00:00:00.000
Procurementprojectedcompletion
2018-12-01T00:00:00.000
Procurementadjustedcompletion
2019-05-01T00:00:00.000
Procurementactualcompletion
2019-04-01T00:00:00.000
Constructionstart
2019-08-01T00:00:00.000
Constructionprojectedcom
2020-08-01T00:00:00.000
Constructionadjustedcompletion
2021-01-01T00:00:00.000
Constructionactualcompletion
2021-01-01T00:00:00.000
Projectliaison
Steve Simon
Lastupdated
2026-10-02T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Trinity Place, Greenwich Street, Morris Street and Egdar Street