Title
Staten Island General Site Work (RG-315MA1)
Summary
This project will reconstruct play equipment, pavements, fencing, water supply, drainage, site features, and plantings at various parks in Staten Island.
Designpercentcomplete
100.0
Procurementpercentcomplete
100.0
Constructionpercentcomplete
100.0
Designstart
2014-10-01T00:00:00.000
Designprojectedcompletion
2014-12-01T00:00:00.000
Designactualcompletion
2017-04-01T00:00:00.000
Procurementstart
2017-04-01T00:00:00.000
Procurementprojectedcompletion
2018-01-01T00:00:00.000
Procurementactualcompletion
2017-12-01T00:00:00.000
Constructionstart
2018-04-01T00:00:00.000
Constructionprojectedcom
2020-03-01T00:00:00.000
Constructionadjustedcompletion
2020-09-01T00:00:00.000
Constructionactualcompletion
2020-09-01T00:00:00.000
Projectliaison
Katrina Toal
Lastupdated
2026-10-01T00:00:00.000
Fundingsource
Borough PresidentCity CouncilMayoral
Name
Forest Ave., Victory Blvd., bet. Clove Rd. and Brookside Ave., Royal Oak Rd.