{"type":"MultiPoint","coordinates":[[-73.98875351998522,40.69628039465852],[-73.98895440058755,40.69620579494357],[-73.98882989843881,40.69620179455739],[-73.9887644117594,40.69619799702521],[-73.98868476268709,40.69619481041278],[-73.98856363269576,40.69618996178724],[-73.98878049457802,40.69610499365948]]}
Projtitle
Tillary & Adams Street Reconstruction - Brooklyn Gateway-Phase 2
Projectdes
This project will redesign and reconstruct Tillary St. from Cadman Plaza W. to Prince St., Cadman Plaza E. from Red Cross Place to Tillary St. and will create public open spaces.
Projectt 1
CAPITAL RECONSTRUCTION
Projectsta
Completed Project
Designstar
2010/04/30 00:00:00
Construc 2
2018/08/22 00:00:00
Overallsco
General Roadway,Lighting (Standalone)
Safetyscop
Curb Extensions,Median Improvement (Raised or Widened),Bike Lane Hardening,Plaza
Otherscope
Percent for Art,SIP Buildout,Green Opportunities,Federal Funds
Projectjus
The scope of the project includes traffic safety and landscaping improvements within the project limits. On Cadman Plaza East, a security barrier and bike lane will be added creating a public connection between the DUMBO neighborhood and Downtown Brookly
Fromstreet
TILLARY STREET
Oftcode
311800385630000000
Latitude
40.6961965351633
Longitude
-73.988761588676