Change Orders Cycle Time and Volume

Change orders are agency-authorized, written documents that allow for modifications of a contract while the contract is being performed. Change orders are used to adjust the value of the contract or the time for performance, and are classified as either construction change orders or design change orders depending on the subject matter of a particular change order. Change orders allow the vendor to complete work included in the scope of the contract. They also allow the agency to make non-material changes to the scope, such as accounting for site conditions that were unknown at the time of contracting. This report includes aggregate, annual count and dollar amount of change orders by City agency.

Business Mayor's Office of Contract Services (MOCS) Dataset a2w2-wg79 8 fields
DOWNLOAD CSV
Dataset fields
Showing 2 real records
DOT
Fiscal Year: 2020 • Change Order Type: Design Change Order • Agency: DOT
Fiscal Year
2020
Change Order Type
Design Change Order
Agency
DOT
Count
6
Original Contract Value
45505038.51
Change Order Contract Value
5287543.37
Change Order Contract In
0.12
Days Processing In Fiscal
52
DSNY
Fiscal Year: 2020 • Change Order Type: Design Change Order • Agency: DSNY
Fiscal Year
2020
Change Order Type
Design Change Order
Agency
DSNY
Count
3
Original Contract Value
15220425.00
Change Order Contract Value
4962423.66
Change Order Contract In
0.33
Days Processing In Fiscal
13