Capital Projects Dashboard - Citywide Budget and Schedule

All major capital infrastructure projects with a committed budget. Financial information and agency schedule details for each project are joined via FMS ID. Only projects in the design phase or later have project schedules displayed. This dataset is part of the Capital Projects Dashboard.

Note: Each row is uniquely identified by its Financial Management Service (FMS) ID. FMS ID is the unique ID that OMB uses for the FMS (Financial Information System). This ID can be universally joined with any OMB dataset that has the same field. The Capital Projects Dashboard is the result of joining OMB’s fiscal data with the agency’s schedule data. FMS IDs and agency projects don't always have a one-to-one relationship (i.e., one project schedule may correlate to multiple FMS IDs, and one FMS may correct to multiple projects with different schedules).

City Government Mayor's Office of Operations (OPS) Dataset fb86-vt7u 27 fields
DOWNLOAD CSV
Dataset fields
Showing 50 real records
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST030-015
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST030-015
Total Budget
449990.59
Spend To Date
352048.15
Spend To Date 1
0.7823
Fms Project Name
Support Center for High Performance Computer
Current Phase
(Completed)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST031-015
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST031-015
Total Budget
3149918.78
Spend To Date
3083654.31
Spend To Date 1
0.9789
Fms Project Name
Soccer Field Lighting and Bleachers
Current Phase
(Completed)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST032-015
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST032-015
Total Budget
627186.00
Spend To Date
457735.32
Spend To Date 1
0.7298
Fms Project Name
Media Culture Screening Room
Current Phase
(Completed)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D005, HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST034-016
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST034-016
Total Budget
125000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
High Performance Computer Center
Current Phase
(Pre-Design)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST035-016
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST035-016
Total Budget
700143.00
Spend To Date
65328.78
Spend To Date 1
0.0933
Fms Project Name
Storage Facility Improvements
Current Phase
(Pending)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST039-019
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST039-019
Total Budget
2136160.00
Spend To Date
202160.00
Spend To Date 1
0.0946
Fms Project Name
Maker Space Lab
Current Phase
(Pending)
Borough
Staten Island
Community Board
Staten Island, Staten Island 02
Budget Line
HN-D300, HN-R001
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: ST041-020
Reporting Period
202305
Managing Agency
CUNY
Fms Id
ST041-020
Total Budget
1250000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Room Conversion for the Genomic Research Center
Current Phase
(Pre-Design)
Borough
Staten Island
Community Board
Staten Island
Budget Line
HN-D300, HN-R001
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: WFF-CUNY
Reporting Period
202305
Managing Agency
CUNY
Fms Id
WFF-CUNY
Total Budget
590237.00
Spend To Date
426360.87
Spend To Date 1
0.7223
Current Phase
(Pending)
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC001-010
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC001-010
Total Budget
448000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
YORK COLLEGE - DISABLED ACCESS UPGRADE
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC001-021
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC001-021
Total Budget
1035000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Track & Field Renovations
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC001-022
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC001-022
Total Budget
1000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Track and Field Renovation
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC002-023
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC002-023
Total Budget
1500000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Tennis Court & Field Office Restroom Renovation
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC006-010
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC006-010
Total Budget
140440.00
Spend To Date
129440.00
Spend To Date 1
0.9216
Fms Project Name
NEW LIGHTING FOR MAIN STAGE THEATER
Current Phase
(Completed)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D004
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC008-022
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC008-022
Total Budget
2000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Track & Field Facility Upgrades
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC022-007
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC022-007
Total Budget
411000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Financial Aid Office Renovation
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens 11
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC025-008
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC025-008
Total Budget
3371609.88
Spend To Date
3312226.14
Spend To Date 1
0.9823
Fms Project Name
SCIENCE FACILITY UPGRADES
Current Phase
(Completed)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300, HN-Q300, HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC027-008
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC027-008
Total Budget
199000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
EXTERIOR BEAUTIFICATION, YORK COLLEGE
Current Phase
(Pending)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-Q006
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC028-008
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC028-008
Total Budget
145000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
IMPROVEMENTS TO THE PERFORMING ARTS CENTER
Current Phase
(Equipment)
Borough
Queens
Community Board
Queens
Budget Line
HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC029-009
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC029-009
Total Budget
2425840.99
Spend To Date
2337698.23
Spend To Date 1
0.9636
Fms Project Name
GREENHOUSE RENOVATION
Current Phase
(Completed)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC035-011
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC035-011
Total Budget
2985469.00
Spend To Date
2971466.60
Spend To Date 1
0.9953
Fms Project Name
New Media Lecture Hall
Current Phase
(Completed)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC043-013
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC043-013
Total Budget
150000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Daycare Facility Improvements
Current Phase
(Equipment)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC049-014
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC049-014
Total Budget
200000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Renovate/Build 3D Graphics and Printing Lab
Current Phase
(Equipment)
Borough
Queens
Community Board
Queens, Queens 12
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC051-015
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC051-015
Total Budget
484000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Performing Arts Center Renovations
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC052-016
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC052-016
Total Budget
3983689.06
Spend To Date
1934961.71
Spend To Date 1
0.4857
Fms Project Name
Laboratory and Classroom Upgrades
Current Phase
(Pending)
Borough
Queens
Community Board
Queens 12
Budget Line
HN-D300, HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC054-017
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC054-017
Total Budget
640000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Greenhouse Renovation
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC055-017
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC055-017
Total Budget
2000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Digital Convergence Center
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC059-019
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC059-019
Total Budget
3811450.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Renovation to Track
Current Phase
(Pending)
Borough
Queens
Community Board
Queens 11
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC061-020
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC061-020
Total Budget
9104785.00
Spend To Date
7027785.00
Spend To Date 1
0.7718
Fms Project Name
Performing Arts Center Upgrades
Current Phase
(Completed)
Borough
Queens
Community Board
Queens 11
Budget Line
HN-D300, HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Fms Id: YC063-020
Reporting Period
202305
Managing Agency
CUNY
Fms Id
YC063-020
Total Budget
2000000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Recapture Academic Space
Current Phase
(Pre-Design)
Borough
Queens
Community Board
Queens
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
72
Fms Id
BY015-007
Total Budget
5200000.00
Spend To Date
5200000.00
Spend To Date 1
1.00
Agency Project Name
BKLYNC-Performing Arts Center
Agency Project Description
Create the core and shell construction of a four-story plus basement infill building containing approximately 66,000 GSF as well as the construction and fit out of a new black box theater.
Current Phase
Close-out
Actual Design Start
2013-12-31T00:00:00.000
Actual Design End
2014-12-31T00:00:00.000
Actual Construction
2013-12-31T00:00:00.000
Actual Construction 1
2014-12-31T00:00:00.000
Actual Construction Start
2015-03-02T00:00:00.000
Actual Construction End
2018-07-03T00:00:00.000
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
73
Fms Id
BA015-014
Total Budget
1250000.00
Spend To Date
1250000.00
Spend To Date 1
1.00
Agency Project Name
BARUCH-17 Lexington Avenue
Agency Project Description
Phase 1 of multi-phased renovation.  Scope includes building-wide infrastructure upgrade and renovated Lexington Avenue lobby with 6 new elevators and full ADA accessibility.
Current Phase
Close-out
Actual Construction Start
2014-02-01T00:00:00.000
Actual Construction End
2016-06-01T00:00:00.000
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
74
Fms Id
CA202HS04
Total Budget
1628826.00
Spend To Date
636848.61
Spend To Date 1
0.3909
Fms Project Name
ADA Improvements
Agency Project Name
HTSCC-ADA Work
Agency Project Description
Bathroom renovations to meet ADA requirements. Project almost complete but currently on hold until legal issues are resolved.
Current Phase
Close-out
Actual Design Start
2008-06-11T00:00:00.000
Actual Design End
2009-01-19T00:00:00.000
Actual Construction Start
2010-01-19T00:00:00.000
Actual Construction End
2010-12-20T00:00:00.000
Borough
Bronx
Community Board
Bronx 05
Budget Line
HN-0206, HN-D002
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
75
Fms Id
HS022-005
Total Budget
400000.00
Spend To Date
300332.17
Spend To Date 1
0.7508
Agency Project Name
HTSCC-HVAC Work
Agency Project Description
Consists of Two Separate Projects: Phase I provided the replacement of (2) 15-ton chillers for 475 GC (complete). Phase II will be replacing HVAC system currently serving the Admin Building.
Current Phase
Pre-Design
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
76
Fms Id
BY026-013
Total Budget
5797200.00
Spend To Date
5797200.00
Spend To Date 1
1.00
Fms Project Name
Renovation of Ingersoll Extension
Agency Project Name
BKLYNC-ADA Upgrade
Agency Project Description
For design and construction of ADA upgrades to three lecture halls located in Boylan and Whitehead Hall. To reconstruct the lecture hall to comply with current ADA codes including minor modifications to the existing A/V systems and all other areas affected by this work. CUNY will perform the work and DASNY will reimburse CUNY.
Current Phase
(Pending)
Forecast Current Phase End
2023-12-29T00:00:00.000
Actual Design Start
2017-03-01T00:00:00.000
Actual Design End
2019-06-28T00:00:00.000
Actual Construction Start
2020-01-01T00:00:00.000
Actual Construction End
2020-06-01T00:00:00.000
Borough
Brooklyn
Community Board
Brooklyn 14
Budget Line
HN-D300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
77
Fms Id
CA028-012
Total Budget
500374.00
Spend To Date
462374.00
Spend To Date 1
0.924
Fms Project Name
University Information Technology Training Center
Agency Project Name
Central Office - Data Center
Agency Project Description
Renovate and upgrade the existing defunct data center for new offices
Current Phase
Construction
Current Phase Start
2016-05-01T00:00:00.000
Forecast Current Phase End
2023-06-01T00:00:00.000
Forecast Completion
2023-06-01T00:00:00.000
Actual Design Start
2013-03-01T00:00:00.000
Actual Design End
2016-01-07T00:00:00.000
Actual Construction Start
2016-05-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HN-D004
Ten Year Plan Category
DATA PROCESSING AND OTHER EQUIPMENT
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
78
Fms Id
MC024-008
Total Budget
1700356.00
Spend To Date
71955.31
Spend To Date 1
0.0423
Fms Project Name
LIGHTING AND ELECTRICAL UPGRADE IN THEATERS
Agency Project Name
BMCC - Upgrades to Theatres
Agency Project Description
Project to provide new rigging and sound systems for all of the theatres at BMCC. Additionally, the lighting will be upgraded and wheelchair access to the backstage area will be undertaken in Theatre 1.
Current Phase
Design
Current Phase Start
2012-11-01T00:00:00.000
Forecast Current Phase End
2023-12-01T00:00:00.000
Forecast Completion
2024-12-01T00:00:00.000
Actual Design Start
2012-11-01T00:00:00.000
Borough
Manhattan
Community Board
Manhattan
Budget Line
HN-D002
Ten Year Plan Category
DATA PROCESSING AND OTHER EQUIPMENT
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
79
Fms Id
CA019HS01
Total Budget
325188.78
Spend To Date
246409.29
Spend To Date 1
0.7577
Fms Project Name
450 Grand Concourse Fire Alarm System
Agency Project Name
HTSCC 450 GC FA Upgrade
Agency Project Description
Upgrade whole building fire alarm system.
Current Phase
Construction
Forecast Current Phase End
2023-12-31T00:00:00.000
Forecast Completion
2023-10-31T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HN-D005
Ten Year Plan Category
DATA PROCESSING AND OTHER EQUIPMENT
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
80
Fms Id
BX031-009
Total Budget
2497507.00
Spend To Date
2380779.36
Spend To Date 1
0.9532
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Agency Project Description
Install new fire alarm systems in 16 buildings
Current Phase
Construction
Current Phase Start
2021-03-01T00:00:00.000
Forecast Current Phase End
2023-12-30T00:00:00.000
Forecast Completion
2024-06-01T00:00:00.000
Actual Design Start
2014-07-17T00:00:00.000
Actual Design End
2020-02-04T00:00:00.000
Actual Construction
2020-02-05T00:00:00.000
Actual Construction 1
2021-01-10T00:00:00.000
Actual Construction Start
2021-03-01T00:00:00.000
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
80
Fms Id
CA054BX18
Total Budget
6973000.00
Spend To Date
3628475.06
Spend To Date 1
0.5203
Agency Project Name
BRXCC - Campus Wide Fire Alarm
Agency Project Description
Install new fire alarm systems in 16 buildings
Current Phase
Construction
Current Phase Start
2021-03-01T00:00:00.000
Forecast Current Phase End
2023-12-30T00:00:00.000
Forecast Completion
2024-06-01T00:00:00.000
Actual Design Start
2014-07-17T00:00:00.000
Actual Design End
2020-02-04T00:00:00.000
Actual Construction
2020-02-05T00:00:00.000
Actual Construction 1
2021-01-10T00:00:00.000
Actual Construction Start
2021-03-01T00:00:00.000
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
81
Fms Id
CA055QB17
Total Budget
4650059.00
Spend To Date
2782132.34
Spend To Date 1
0.5983
Fms Project Name
CUNY ASAP Expansion
Agency Project Name
QNBCC-Purchase Cloverdale
Agency Project Description
Purchase the building at 50-35 Cloverdale Blvd at Oakland Gardens, Queens
Current Phase
(Pending)
Borough
Queens
Community Board
Queens
Budget Line
HN-0206, HN-Q001
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
82
Fms Id
CL018-015
Total Budget
1250669.00
Spend To Date
887326.41
Spend To Date 1
0.7094
Fms Project Name
Trial Practice Room
Agency Project Name
CUNY School of Law 2 Court
Agency Project Description
Project to convert a classroom into a fully equipped Trial Courtroom for mock trial instruction.
Current Phase
(Equipment)
Actual Design Start
2017-03-01T00:00:00.000
Actual Design End
2019-06-28T00:00:00.000
Actual Construction Start
2020-01-01T00:00:00.000
Actual Construction End
2022-11-30T00:00:00.000
Borough
Queens
Community Board
Queens
Budget Line
HN-Q300
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
83
Fms Id
CA091LG19
Total Budget
2250000.00
Spend To Date
0.00
Spend To Date 1
0.00
Agency Project Name
LGCC - Schenker M Bldg
Agency Project Description
M Building / Shenker Hall fire alarm upgrade
Current Phase
Design
Current Phase Start
2013-04-01T00:00:00.000
Actual Design Start
2013-04-01T00:00:00.000
Actual Design End
2021-06-01T00:00:00.000
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
84
Fms Id
HS054-017
Total Budget
7648000.00
Spend To Date
6713087.77
Spend To Date 1
0.8777
Fms Project Name
Create one Stop Center -425 Grand Concourse
Agency Project Name
Eugenio Maria De Hostos Com. College - 425 GC ASAP Program
Agency Project Description
Full build-out of leased space at 425 Grand Concourse.  Program will relocate and expand the ASAP Program, Student Access Coaching Unit, and Accessibility Resource Center.
Current Phase
Close-out
Actual Design Start
2022-07-05T00:00:00.000
Actual Design End
2022-12-30T00:00:00.000
Actual Construction Start
2021-12-01T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HN-D002
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: CUNY • Sponsor Agency: CUNY
Reporting Period
202305
Managing Agency
CUNY
Sponsor Agency
CUNY
Pid
85
Fms Id
CA022BX01
Total Budget
40100000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
Bronx CC HVAC Improvements
Agency Project Name
BRXCC - HVAC Upgrades - CUNY
Agency Project Description
Install new ventilation systems with heating and cooling to seven buildings
Current Phase
Design
Forecast Current Phase End
2023-12-30T00:00:00.000
Forecast Completion
2025-01-30T00:00:00.000
Borough
Bronx
Community Board
Bronx
Budget Line
HN-0206, HN-D002, HN-D003, HN-D004
Ten Year Plan Category
MISCELLANEOUS RECONSTRUCTION
Agency Data Date
2023-04-26T00:00:00.000
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: 70MULB1
Reporting Period
202305
Managing Agency
DCAS
Fms Id
70MULB1
Total Budget
6569555.00
Spend To Date
4363747.81
Spend To Date 1
0.6642
Fms Project Name
70 MULBERRY - DEMOLITION
Current Phase
(Pending)
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
RE-0025
Ten Year Plan Category
REHABILITATION OF NON-WATERFRONT PROPERTIES
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: ACEDCA212
Reporting Period
202305
Managing Agency
DCAS
Fms Id
ACEDCA212
Total Budget
943000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
DCLA - Met - Special Exhibition Lighting Improvement
Current Phase
(Pending)
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
PU-0025
Ten Year Plan Category
BUILDING CONSTRUCTION, RECONSTRUCTION OR RETROFIT
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: ACEDCA213
Reporting Period
202305
Managing Agency
DCAS
Fms Id
ACEDCA213
Total Budget
6785000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
DCLA - AMNH - S3A Air Handling Unit
Current Phase
(Pending)
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
PU-0025
Ten Year Plan Category
BUILDING CONSTRUCTION, RECONSTRUCTION OR RETROFIT
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: ACEDCA214
Reporting Period
202305
Managing Agency
DCAS
Fms Id
ACEDCA214
Total Budget
22297000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
DCLA - Met Museum - HVAC and Envelope Improvements to Renov
Current Phase
(Pending)
Borough
Manhattan
Community Board
Manhattan 01
Budget Line
PU-0025
Ten Year Plan Category
BUILDING CONSTRUCTION, RECONSTRUCTION OR RETROFIT
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: ACEDCA221
Reporting Period
202305
Managing Agency
DCAS
Fms Id
ACEDCA221
Total Budget
1566000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
DCLA - NYBG CHILLER REPLACMENT, WATER SYSTEM OPTIMIZATION
Current Phase
(Pending)
Borough
Bronx
Community Board
Bronx 01
Budget Line
PU-0025
Ten Year Plan Category
MISCELLANEOUS ENERGY EFFICIENCY AND SUSTAINABILITY
Fms Data Date
2023-05-11T00:00:00.000
202305
Reporting Period: 202305 • Managing Agency: DCAS • Fms Id: ACEDCA222
Reporting Period
202305
Managing Agency
DCAS
Fms Id
ACEDCA222
Total Budget
333000.00
Spend To Date
0.00
Spend To Date 1
0.00
Fms Project Name
DCLA - BRONX ZOO ADMIN WEST AHU - 2300 SOUTHERN BLVD, BX
Current Phase
(Pending)
Borough
Bronx
Community Board
Bronx 01
Budget Line
PU-0025
Ten Year Plan Category
MISCELLANEOUS ENERGY EFFICIENCY AND SUSTAINABILITY
Fms Data Date
2023-05-11T00:00:00.000