Project Name
Red Flag Repairs on Van Wyck Expressway Viaduct
Project Received Date
2016-04-22T00:00:00.000
Project Id Number Op
XM17.21 D263048 D263267
Project Description Type
Engineering red and yellow flag spot repairs on the viaduct of the Van Wyck expressway under a "Where and When" contract. These are categorized as emergencies but most of these work orders are 2+ years old, because the system is that woefully broken. Work is pushed into the contract on a rolling basis; this is a WO contract.
Only park impact is rolling closure of a few parking spaces at a time for a day or so at a time.
Impacted Park Name S
Flushing Meadows Corona Park;
Address Intersection
131 St & Avery Ave
Multisite Project
Single Site
Sponsoring Agency Entity
SDOT
Primary Scope Of Work
Bridge Component Rehabilitation
Impacted Parks Division S
Borough Operations
Park Impact Type
Access-Only
Current Phase
Presumed Complete
Construction Manager Op
Area Supervisor
Construction Manager Company Op
NYSDOT
Expected Construction End Date Op
2016-07-19T00:00:00.000
Actual Construction End Date Op
2018-08-13T00:00:00.000
Contractor For Construction Permit Firm Name
El Sol
Construction Permit Request Received Date
2016-05-23T00:00:00.000
Construction Permit Id
Q099.20160609
Latest Site Visit
2016-05-19T00:00:00.000
Forestry Permit Status
Not Required
Construction Permit Special Conditions
i. One location at a time: At any given time, contractor may occupy not more than one of the four permitted work locations in the park.
ii. Order of sites: Piers are to be completed in the following order: Pier 20; then Pier 66; then remaining piers 39 and 43.
iii. Work embargos:
a) After August 1, no work or laydown is permitted at Pier 20 or Pier 66.
b) Work is prohibited at all sites during weekends and holidays (existing laydown is permitted)
iv. Delivery embargos: delivery to work sites is prohibited during the following days (existing laydown is permitted)
a) All Weekends
b) June 7th after 2pm
c) June 8th after 2pm
d) June 22nd
e) July 6th
f) July 28th
g) August 11th
Borough Approval Date
2017-09-28T00:00:00.000
Permit Issuance Date
2016-06-09T00:00:00.000
Permit Start Date
2016-06-06T00:00:00.000
Original Permit Expiration Date
2016-08-01T00:00:00.000
Latest Permit Extension Amendment Request Date
2018-06-29T00:00:00.000
Latest Permit Extension Amendment Issuance Date
2017-09-28T00:00:00.000
Latest Permit Expiration Date
2017-12-01T00:00:00.000
Permit Amendment Content
Ext 3Ext 2D263048 Work Orders No. 144, 147 & 149 are deemed included.1.C. “Special Conditions” are as follows:i. One location at a time: At any given time, contractor may occupy not more than one of the three permitted work locations in the park.ii. No weekend work: Work is prohibited at all sites during weekends and holidays (existing laydown is permitted).iii. Provide Schedule: Three business days in advance of work, provide schedule of work to jonathan.landsman@parks.nyc.gov. You need not wait for an approval of schedule to proceed with work.Ext 11.C. “Special Conditions” are amended as follows:ii. Order of Sites: Pier 66 must be completed first. Following 66, work is to then proceed southward through the piers, with only one location occupied or worked on at a time.iii. Blackout Dates: No sites may be occupied in any manner or worked on between September 30 and October 2nd, inclusive.iv. Delivery Embargoes: This section is deleted.
Substantial Completion Date Op
2018-08-13T00:00:00.000
Created
2016-06-03T09:39:00.000
Modified
2019-11-05T15:13:00.000
Coordinates
40.751658, -73.836042