Project Name
Rehabilitation of Grand Concourse Bridge over Metro-North Railroad Hudson Line
Project Received Date
2017-05-18T00:00:00.000
Project Id Number Op
HBX1190
Project Description Type
Bridge rehab project in five stages. Despite this being "rehab" and leaving abutments in place, this is a five-stage, very complex job on a bridge that is partly supported by subway trusses and carries a gas line, con-ed ducts, water main, telephone and cable, FDNY alarm posts, and abuts heavy ped generating facilities (park and school).
Impacted Park Name S
Franz Sigel Park;
Address Intersection
Grand Course between East 151st and East 153rd Street
Multisite Project
Single Site
Sponsoring Agency Entity
CDOT
Primary Scope Of Work
Bridge Component Rehabilitation
Impacted Parks Division S
Borough Operations;#Borough Forestry
Park Impact Type
Staging;#Partial Park Closure
Design Consultant Op
Michael Baker Engineering, Inc.
Public Design Commission Approval Required
No
Mass Mailing 3 Received Date
2020-03-26T00:00:00.000
Design Completion Date Op
2019-03-01T00:00:00.000
Construction Manager Op
EIC/Deputy Director
Construction Manager Company Op
NYCDOT
Construction Kickoff Op
2020-05-21T00:00:00.000
Contractor For Construction Permit Firm Name
CAC Industries Inc.
Construction Permit Request Received Date
2020-07-02T00:00:00.000
Construction Permit Id
X047.20200708
Latest Site Visit
2020-07-01T00:00:00.000
Forestry Permit Status
Pending
Construction Permit Special Conditions
i. Parks will allow Permittee to stage for one year only. A permit extension may be considered depending on the schedule of Parks’ capital project. The area must be vacated as soon as Parks’ capital project is ready to begin. See Attachment B for staging layout.
ii. Permittee must restore the lawn per the specifications in Attachment D. Permittee must water the area to ensure lawn establishment.
iii. Staging on the basketball court is not allowed. Sightlines into the court must be maintained.
iv. Pedestrian path must remain open and access to the basketball court must be maintained.
v. The water line must be protected during construction. If damaged, Permittee will replace it at no cost to the City.
vi. When the large stones are removed from the Franz Sigel staging area, Permittee will transport them to Bridge Park South for storage. Contractor will coordinate with Bronx M&O on a date/time for delivering the stones.
Permit Start Date
2020-10-13T00:00:00.000
Original Permit Expiration Date
2021-08-31T00:00:00.000
Created
2018-12-07T12:43:00.000
Modified
2020-10-09T12:35:00.000
Coordinates
40.820994, -73.926394