Project Name
PS 271K Temporary Boiler and Oil Tank
Project Received Date
2018-07-16T00:00:00.000
Project Description Type
Staging of a temporary boiler and oil tank within a portion of Fish Playground
to facilitate heating system upgrades at PS 271K
Impacted Park Name S
Fish Playground;
Multisite Project
Single Site
Sponsoring Agency Entity
SCA
Primary Scope Of Work
Public Building
Impacted Parks Division S
Borough Operations;#Borough Forestry
Current Phase
Presumed Complete
Contractor For Construction Permit Firm Name
Central Mechanical Systems Inc.
Construction Permit Request Received Date
2018-07-16T00:00:00.000
Construction Permit Id
B325.20180809
Forestry Permit Status
Approved
Forestry Permit Id Number
I18-036
Construction Permit Special Conditions
No anchoring of any kind shall be permitted on existing paved surfaces within the playground.
Temporary perimeter fences should utilize water-filled or other similar low-impact footings.
Permittee shall notify Parks at least 48 hours prior to mobilization so that Parks can arrange to
be present during the delivery of trailers, if deemed necessary.
Permittee shall protect existing asphalt surfaces from damage during mobilization, staging, and
demobilization. Trailers should be staged on plywood, wood blocks, etc. to limit the impact of
the equipment on existing asphalt surfaces.
The uppermost section of chain link fence fabric along the south fence, in the area directly
adjacent to the school’s existing boiler room, may be cut and rolled back to provide access for
piping and other necessary connections between the temporary boiler and the school facility.
Permittee shall notify Parks ahead of all scheduled fuel deliveries, if such deliveries require
access through the playground.
Permit Start Date
2018-08-13T00:00:00.000
Original Permit Expiration Date
2019-10-31T00:00:00.000
Created
2018-08-20T12:45:00.000
Modified
2020-08-28T12:27:00.000
Coordinates
40.678154, -73.915437